Amrut 2.0 (2022-23)-Augmentation and Rehabilitation of water supply system-UIDSSMT WSS to Kalpetta municipality- Providing water supply with household water tap connection to Kalpetta municipality.

Project Amrut 2.0 (2022-23)-Augmentation and Rehabilitation of water supply system-UIDSSMT WSS to Kalpetta municipality- Providing water supply with household water tap connection to Kalpetta municipality.
Project Code WYDAMRUT 2022213827
Type Main project
Funding Agency AMRUT 2
Category AMRUT
Type of scheme Water Supply
Scheme
Description Augmentation and Rehabilitation of water supply system-UIDSSMT WSS to Kalpetta municipality- Providing water supply with household water tap connection to Kalpetta municipality.
Status On-going
District Wayanad
Executing Office Kalpetta PH Sn 1
AS Amount (Rs) 52880000
AS Number G.O.(Rt)No.473/2023/LSGD
TS Amount (Rs) 49500000
TS Number TS/744/2022_26_1_1
Total Bill Submitted (Rs) 13191519
Total Bill Paid (Rs) 13191519
Population Benefitted 500
Capacity in MLD 5.00
Actual Project Completion Date Date is not specified
Coverage nil
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Amrut 2.0(2022-23)-Augmentation and Rehabilitation of water supply system-UIDSSMT WSS to Kalpetta municipality- Providing water supply with household water tap connection to Kalpetta municipality. Kalpetta PH Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 May 2024 32593m laid. 1039 Connections given. Work 90% completed.2nd & Part bill submitted. Kalpetta PH Sn 1 - AE
08 May 2024 32593m laid. 1039 Connections given. Work 87% completed.2nd & Part bill submitted Kalpetta PH Sn 1 - AE
03 May 2024 32500m laid. 1010 Connections given. Work 87% completed.2nd & Part bill submitted Kalpetta PH Sn 1 - AE
25 Apr 2024 30000m laid. 1010 Connections given. Work 87% completed.2nd & Part bill submitted Kalpetta PH Sn 1 - AE
23 Apr 2024 30000m laid. 1010 Connections given. Work 85% completed.2nd & Part bill submitted. Kalpetta PH Sn 1 - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 23/02/2023
Scheduled date of Completion of the Project 09 Apr 2024
Expected date of Completion 30/06/2024

Processing Dates

AS Date 23 Feb 2023
TS Date 08 May 2023

Other details

Project Officers View