Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission - Aranmula Panchayath

Project Jal Jeevan Mission - Aranmula Panchayath
Project Code PTAJJM052212138
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Design and Construction of 8.5 mld Treatment plant near Paruthanpara in Aranmula Panchayath including 6 LL Sump. Laying Raw water pumping main from intake well cum pump house at Malakkara to WTP. Supply and Installation of Clear Water Pump sets / Raw water Pump sets. Design and Construction of Indoor Transformer Substation Building at Well and WTP site Supply and Installation of Indoor Dry type Transformer at Well site and WTP site Design and Construction of 22.50 LL OHSR at Paruthanpara WTP site Design and Laying of Distribution networks Providing FHTC’s in the entire Aranmula Panchayath. Road Restoration and Power allocation charges
Status On-going
District Pathanamthitta
Executing Office Adoor Project Dn
AS Amount (Rs) 837230000
AS Number G.O.(Rt)No.401/2022/WRD
TS Amount (Rs) 416642
TS Number TS/2022-2023/2022/7673
Total Bill Submitted (Rs) 31118152
Total Bill Paid (Rs)
Population Benefitted 33548
Capacity in MLD 8.50
Actual Project Completion Date Date is not specified
Coverage Work is based on providing 8387 nos of FHTC's
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM-5th SWSM-Supplying and laying distribution system and providing 8187 FHTCs in Aranmula Panchayat including road restoration works Adoor Project Dn
2 JJM - RWSS to Aranmula - Investigation survey of all roads in Aranmula Panchayath Adoor Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Sep 2022 Surveying of all roads including PWD/ LSGD roads is competed Adoor Project Dn AE2
01 Sep 2022 Survey Work has been completed | 100% Completed | 19/08/2022 Surveying of all roads including PWD/ LSGD roads is competed Adoor Project Dn AE2
01 Sep 2022 Work has been completed | 100% Completed | 19/08/2022 Surveying of all roads including PWD/ LSGD roads is competed Adoor Project Dn AE2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 05/05/2022
Scheduled date of Completion of the Project 31 Dec 2025
Expected date of Completion 31/12/2023

Processing Dates

AS Date 13 May 2022
TS Date 08 Mar 2022

Other details

Project Officers View