KIIFB-CWSS to Vithura and Tholicode villages - PART 1 (Moonam nuber to Makki Jn) PART 2 (Makki Jn to Jersifarm)
Project |
KIIFB-CWSS to Vithura and Tholicode villages - PART 1 (Moonam nuber to Makki Jn) PART 2 (Makki Jn to Jersifarm) |
Project Code |
TVMDEPO12219082 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
KIIFB-CWSS to Vithura and Tholicode villages - PART 1 (Moonam nuber to Makki Jn) PART 2 (Makki Jn to Jersifarm) |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Palod WS Sn |
AS Amount (Rs) |
13400000
|
AS Number |
ch no.535159 |
TS Amount (Rs) |
11740000 |
TS Number |
16781/2021-2022,16779/2021-2022 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
1000 |
Capacity in MLD |
350.00 |
Actual Project Completion Date |
31 May 2024 |
Coverage |
Relaying of distribution lines of 200mm DI K9 pipe & 160mm pvc (10kg/cm2)pipe from Theviyodu jn to Vithura Jersifarm due to Vithura-Bonacaud road widening project |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB-CWSS to Vithura and Tholicode villages - Relaying of distribution lines of 160mm pvc (10kg/cm2)pipe from Theviyodu jn to Vithura Jersifarm due to Vithura-Bonacaud road widening project PART 1(Moonam nuber to Makki Jn) |
Palod WS Sn |
|
2 |
KIIFB-CWSS to Vithura and Tholicode villages - Relaying of distribution lines of 200mm DI K9 pipe & 160mm pvc (10kg/cm2)pipe from Theviyodu jn to Vithura Jersifarm due to Vithura-Bonacaud road widening project PART 2(Makki Jn to Jersiform) |
Palod WS Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 May 2024 |
Work completed |
Palode AE |
|
13 May 2024 |
Part 2 completed & part 1 delayed for handovering the site from KRFB |
Palode AE |
|
08 May 2024 |
Part 2 completed & part 1 delayed for handovering the site from KRFB |
Palode AE |
|
03 May 2024 |
Part 2 completed & part 1 delayed for handovering the site from KRFB |
Palode AE |
|
28 Apr 2024 |
Part 2 completed & part 1 delayed for handovering the site from KRFB |
Palode AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
25/01/2022 |
Scheduled date of Completion of the Project |
24 May 2022 |
Expected date of Completion |
24/05/2022 |
Processing Dates
AS Date |
28 Dec 2021 |
TS Date |
31 Dec 2021 |