KIIFB-CWSS to Vithura and Tholicode villages - PART 1 (Moonam nuber to Makki Jn) PART 2 (Makki Jn to Jersifarm)

Project KIIFB-CWSS to Vithura and Tholicode villages - PART 1 (Moonam nuber to Makki Jn) PART 2 (Makki Jn to Jersifarm)
Project Code TVMDEPO12219082
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description KIIFB-CWSS to Vithura and Tholicode villages - PART 1 (Moonam nuber to Makki Jn) PART 2 (Makki Jn to Jersifarm)
Status Completed
District Thiruvananthapuram
Executing Office Palod WS Sn
AS Amount (Rs) 13400000
AS Number ch no.535159
TS Amount (Rs) 11740000
TS Number 16781/2021-2022,16779/2021-2022
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 1000
Capacity in MLD 350.00
Actual Project Completion Date 31 May 2024
Coverage Relaying of distribution lines of 200mm DI K9 pipe & 160mm pvc (10kg/cm2)pipe from Theviyodu jn to Vithura Jersifarm due to Vithura-Bonacaud road widening project
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB-CWSS to Vithura and Tholicode villages - Relaying of distribution lines of 160mm pvc (10kg/cm2)pipe from Theviyodu jn to Vithura Jersifarm due to Vithura-Bonacaud road widening project PART 1(Moonam nuber to Makki Jn) Palod WS Sn
2 KIIFB-CWSS to Vithura and Tholicode villages - Relaying of distribution lines of 200mm DI K9 pipe & 160mm pvc (10kg/cm2)pipe from Theviyodu jn to Vithura Jersifarm due to Vithura-Bonacaud road widening project PART 2(Makki Jn to Jersiform) Palod WS Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 May 2024 Work completed Palode AE
13 May 2024 Part 2 completed & part 1 delayed for handovering the site from KRFB Palode AE
08 May 2024 Part 2 completed & part 1 delayed for handovering the site from KRFB Palode AE
03 May 2024 Part 2 completed & part 1 delayed for handovering the site from KRFB Palode AE
28 Apr 2024 Part 2 completed & part 1 delayed for handovering the site from KRFB Palode AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 25/01/2022
Scheduled date of Completion of the Project 24 May 2022
Expected date of Completion 24/05/2022

Processing Dates

AS Date 28 Dec 2021
TS Date 31 Dec 2021