Jal Jeevan Mission -2020-21 -Laying distribution system and providing FHTCs (800 Nos) in Mundur panchayath Zone 6 from the 8LL OHSR at Mundur panchayath office compound Phase-III

Project Jal Jeevan Mission -2020-21 -Laying distribution system and providing FHTCs (800 Nos) in Mundur panchayath Zone 6 from the 8LL OHSR at Mundur panchayath office compound Phase-III
Project Code PKDJJM022213216
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission -2020-21 -Laying distribution system and providing FHTCs (800 Nos) in Mundur panchayath Zone 6 from the 8LL OHSR at Mundur panchayath office compound Phase-III
Status On-going
District Palakkad
Executing Office Chittur Project Dn
AS Amount (Rs) 97000000
AS Number GO(RI) No.134/2022/WRRD Dated:23-02-2022 97000000.00
TS Amount (Rs) 60500000
TS Number TS/2022-2023/2021/35785 Dated: 05-05-2022
Total Bill Submitted (Rs) 7764753
Total Bill Paid (Rs) 7764753
Population Benefitted 30648
Capacity in MLD
Actual Project Completion Date 25 Jan 2023
Coverage Mundur Grramapanchayath

Packages

No. Project Name Location View
1 Jal Jeevan Mission -2020-21 -Laying distribution system and providing FHTCs (800 Nos) in Mundur panchayath Zone 6 from the 8LL OHSR at Mundur panchayath office compound Phase-III Project Division Chittur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 May 2024 Work in progress | 91% Completed | 16/05/2024 9OmmHDPE PIPE- 15.00kM LAID/ out of 16.078 km 2. FHTC-400/OUT OF 800 Nos Chittur Project Dn - AE 2
09 May 2024 Work in progress | 91% Completed | 09/05/2024 9OmmHDPE PIPE- 15.00kM LAID/ out of 16.078 km 2. FHTC-400/OUT OF 800 No Chittur Project Dn - AE 2
02 May 2024 Work in progress | 91% Completed | 02/05/2024 9OmmHDPE PIPE- 15.00kM LAID/ out of 16.078 km 2. FHTC-400/OUT OF 800 No Chittur Project Dn - AE 2
25 Apr 2024 Work in progress | 91% Completed | 25/04/2024 9OmmHDPE PIPE- 15.00kM LAID/ out of 16.078 km 2. FHTC-400/OUT OF 800 No Chittur Project Dn - AE 2
19 Apr 2024 ation Work in progress | 91% Completed | 19/04/2024 9OmmHDPE PIPE- 15.00kM LAID/ out of 16.078 km 2. FHTC-400/OUT OF 800 No Chittur Project Dn - AE 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 26/07/2022
Scheduled date of Completion of the Project 25 Jan 2023
Expected date of Completion 31/12/2023

Processing Dates

AS Date 23 Feb 2022
TS Date 05 May 2022