Jal Jeevan Mission -2020-21 -Laying distribution system and providing FHTCs (800 Nos) in Mundur panchayath Zone 6 from the 8LL OHSR at Mundur panchayath office compound Phase-III
Project |
Jal Jeevan Mission -2020-21 -Laying distribution system and providing FHTCs (800 Nos) in Mundur panchayath Zone 6 from the 8LL OHSR at Mundur panchayath office compound Phase-III |
Project Code |
PKDJJM022213216 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission -2020-21 -Laying distribution
system and providing FHTCs (800 Nos) in Mundur
panchayath Zone 6 from the 8LL OHSR at
Mundur panchayath office compound Phase-III |
Status |
On-going |
District |
Palakkad |
Executing Office |
Chittur Project Dn |
AS Amount (Rs) |
97000000
|
AS Number |
GO(RI) No.134/2022/WRRD Dated:23-02-2022 97000000.00 |
TS Amount (Rs) |
60500000 |
TS Number |
TS/2022-2023/2021/35785 Dated: 05-05-2022 |
Total Bill Submitted (Rs) |
7764753 |
Total Bill Paid (Rs) |
7764753 |
Population Benefitted |
30648 |
Capacity in MLD |
|
Actual Project Completion Date |
25 Jan 2023 |
Coverage |
Mundur Grramapanchayath |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission -2020-21 -Laying distribution system and providing FHTCs (800 Nos) in Mundur panchayath Zone 6 from the 8LL OHSR at Mundur panchayath office compound Phase-III |
Project Division Chittur |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
16 May 2024 |
Work in progress | 91% Completed | 16/05/2024
9OmmHDPE PIPE- 15.00kM LAID/ out of 16.078 km 2. FHTC-400/OUT OF 800 Nos |
Chittur Project Dn - AE 2 |
|
09 May 2024 |
Work in progress | 91% Completed | 09/05/2024
9OmmHDPE PIPE- 15.00kM LAID/ out of 16.078 km 2. FHTC-400/OUT OF 800 No |
Chittur Project Dn - AE 2 |
|
02 May 2024 |
Work in progress | 91% Completed | 02/05/2024
9OmmHDPE PIPE- 15.00kM LAID/ out of 16.078 km 2. FHTC-400/OUT OF 800 No |
Chittur Project Dn - AE 2 |
|
25 Apr 2024 |
Work in progress | 91% Completed | 25/04/2024
9OmmHDPE PIPE- 15.00kM LAID/ out of 16.078 km 2. FHTC-400/OUT OF 800 No |
Chittur Project Dn - AE 2 |
|
19 Apr 2024 |
ation
Work in progress | 91% Completed | 19/04/2024
9OmmHDPE PIPE- 15.00kM LAID/ out of 16.078 km 2. FHTC-400/OUT OF 800 No |
Chittur Project Dn - AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
26/07/2022 |
Scheduled date of Completion of the Project |
25 Jan 2023 |
Expected date of Completion |
31/12/2023 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
05 May 2022 |