State Plan 2017-18 : TSS - Rehabilitation of damaged 400mm sewer line and reconstruction of dilapidated manhole in the sewer line between Thakaraparampu Malloor road
Project |
State Plan 2017-18 : TSS - Rehabilitation of damaged 400mm sewer line and reconstruction of dilapidated manhole in the sewer line between Thakaraparampu Malloor road |
Project Code |
TVMGOK03181763 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Sewerage |
Scheme |
2215-02-106-97 |
Description |
TSS - Rehabilitation of damaged 400mm sewer line and reconstruction of dilapidated manhole in the sewer line between Thakaraparampu Malloor road
AS:-G.O.(Rt.) No. 202/2018/WRD dated 26.03.2018 |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Kuriathy Sewerage Sn 1 |
AS Amount (Rs) |
1900000
|
AS Number |
202/2018/WRD |
TS Amount (Rs) |
1750000 |
TS Number |
7612/2020-2021 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
10000 |
Capacity in MLD |
1.20 |
Actual Project Completion Date |
13 Nov 2021 |
Coverage |
Sreekanteswaram ward -
Pipe line rerouting. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
State Plan 2017-18 : TSS - Rehabilitation of damaged 400mm sewer line and reconstruction of dilapidated manhole in the sewer line between Thakaraparampu Malloor road |
Kuriathy Sewerage Sn 1 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Nov 2021 |
Work completed. |
Kuriathy Sewerage Sn1 AE |
|
10 Nov 2021 |
96 % : Physical work in progress, 29.4/60 M pipe laying completed, 5/5 MH construction completed, Bucket cleaning work completed. The provision for 30M pipe laying in canal road side found unnecessary as there is no breakage in the existing line (During bucket cleaning no hinderence was found). Manhole reconstruction work started in Manacaud - Kaladi road. Dismantling of bituminous road and excavation for MH in progress, work delayed due to rain. |
Kuriathy Sewerage Sn1 AE |
|
08 Nov 2021 |
96 % : Physical work in progress, 29.4/60 M pipe laying completed, 5/5 MH construction completed, Bucket cleaning work completed. The provision for 30M pipe laying in canal road side found unnecessary as there is no breakage in the existing line (During bucket cleaning no hinderence was found). 7th MH work completed in Chettikkulangara road. Manhole reconstruction work started in Manacaud - Kaladi road. |
Kuriathy Sewerage Sn1 AE |
|
04 Nov 2021 |
95% : Physical work in progress, 29.4/60 M pipe laying completed, 5/5 MH construction completed, Bucket cleaning work completed. The provision for 30M pipe laying in canal road side found unnecessary as there is no breakage in the existing line (During bucket cleaning no hinderence was found). 7th MH work completed in Chettikkulangara road. One manhole to be reconstructed in Manacaud - Kaladi road on emergency. Work was planned to started from 02/11/2021, but couldnt commence due to heavy rain forecast. Work rescheduled from 05/11/2021. |
Kuriathy Sewerage Sn1 AE |
|
31 Oct 2021 |
95% : Physical work in progress, 29.4/60 M pipe laying completed, 5/5 MH construction completed, Bucket cleaning work completed. The provision for 30M pipe laying in canal road side found unnecessary as there is no breakage in the existing line (During bucket cleaning no hinderence was found). 7th MH work completed in Chettikkulangara road. One manhole to be reconstructed in Manacaud - Kaladi road on emergency. Work to be started from 02/11/2021. |
Kuriathy Sewerage Sn1 AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
16/06/2021 |
Scheduled date of Completion of the Project |
31 May 2021 |
Expected date of Completion |
15/11/2021 |
Processing Dates
AS Date |
26 Mar 2018 |
TS Date |
20 Sep 2020 |