Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

State Plan 2017-18 : TSS - Rehabilitation of damaged 400mm sewer line and reconstruction of dilapidated manhole in the sewer line between Thakaraparampu Malloor road

Project State Plan 2017-18 : TSS - Rehabilitation of damaged 400mm sewer line and reconstruction of dilapidated manhole in the sewer line between Thakaraparampu Malloor road
Project Code TVMGOK03181763
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Sewerage
Scheme 2215-02-106-97
Description TSS - Rehabilitation of damaged 400mm sewer line and reconstruction of dilapidated manhole in the sewer line between Thakaraparampu Malloor road AS:-G.O.(Rt.) No. 202/2018/WRD dated 26.03.2018
Status Completed
District Thiruvananthapuram
Executing Office Kuriathy Sewerage Sn 1
AS Amount (Rs) 1900000
AS Number 202/2018/WRD
TS Amount (Rs) 1750000
TS Number 7612/2020-2021
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 10000
Capacity in MLD 1.20
Actual Project Completion Date 13 Nov 2021
Coverage Sreekanteswaram ward - Pipe line rerouting.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 State Plan 2017-18 : TSS - Rehabilitation of damaged 400mm sewer line and reconstruction of dilapidated manhole in the sewer line between Thakaraparampu Malloor road Kuriathy Sewerage Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Nov 2021 Work completed. Kuriathy Sewerage Sn1 AE
10 Nov 2021 96 % : Physical work in progress, 29.4/60 M pipe laying completed, 5/5 MH construction completed, Bucket cleaning work completed. The provision for 30M pipe laying in canal road side found unnecessary as there is no breakage in the existing line (During bucket cleaning no hinderence was found). Manhole reconstruction work started in Manacaud - Kaladi road. Dismantling of bituminous road and excavation for MH in progress, work delayed due to rain. Kuriathy Sewerage Sn1 AE
08 Nov 2021 96 % : Physical work in progress, 29.4/60 M pipe laying completed, 5/5 MH construction completed, Bucket cleaning work completed. The provision for 30M pipe laying in canal road side found unnecessary as there is no breakage in the existing line (During bucket cleaning no hinderence was found). 7th MH work completed in Chettikkulangara road. Manhole reconstruction work started in Manacaud - Kaladi road. Kuriathy Sewerage Sn1 AE
04 Nov 2021 95% : Physical work in progress, 29.4/60 M pipe laying completed, 5/5 MH construction completed, Bucket cleaning work completed. The provision for 30M pipe laying in canal road side found unnecessary as there is no breakage in the existing line (During bucket cleaning no hinderence was found). 7th MH work completed in Chettikkulangara road. One manhole to be reconstructed in Manacaud - Kaladi road on emergency. Work was planned to started from 02/11/2021, but couldnt commence due to heavy rain forecast. Work rescheduled from 05/11/2021. Kuriathy Sewerage Sn1 AE
31 Oct 2021 95% : Physical work in progress, 29.4/60 M pipe laying completed, 5/5 MH construction completed, Bucket cleaning work completed. The provision for 30M pipe laying in canal road side found unnecessary as there is no breakage in the existing line (During bucket cleaning no hinderence was found). 7th MH work completed in Chettikkulangara road. One manhole to be reconstructed in Manacaud - Kaladi road on emergency. Work to be started from 02/11/2021. Kuriathy Sewerage Sn1 AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 16/06/2021
Scheduled date of Completion of the Project 31 May 2021
Expected date of Completion 15/11/2021

Processing Dates

AS Date 26 Mar 2018
TS Date 20 Sep 2020

Other details

Project Officers View