WSS to Pavaratty and Mullassery Panchayaths in Chavakkad Taluk of Thrissur District - Construction of 5.50 LL capacity OHSR at Mullassery and 6.70 LL capacity OHSR at Pavaratty panchayath
Project |
WSS to Pavaratty and Mullassery Panchayaths in Chavakkad Taluk of Thrissur District - Construction of 5.50 LL capacity OHSR at Mullassery and 6.70 LL capacity OHSR at Pavaratty panchayath |
Project Code |
TCRGOK0818505 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
WSS to Pavaratty and Mullassery panchayaths in Chavakkadu taluk of Thrissur district.
1) Construction of 6.70 LL capacity OHSR at Pavaratty panchayath
2) Construction of 5.50 LL capacity OHSR at Mullassery panchayath |
Status |
On-going |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
35000000
|
AS Number |
GO (RT) No.615/2018/WRD |
TS Amount (Rs) |
33110000 |
TS Number |
TS/2018-19/2018/4909&4910 |
Total Bill Submitted (Rs) |
30538919 |
Total Bill Paid (Rs) |
161000 |
Population Benefitted |
52081 |
Capacity in MLD |
3.46 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Pavaratty and Mullassery Panchayaths
Population benefitted - 52081 |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Construction of 5.50 LL capacity OHSR at Mullassery Panchayath |
Nattika Project Dn |
|
2 |
Construction of 6.70 LL capacity OHSR at Pavaratty panchayath |
Nattika Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
30 Apr 2024 |
6.70LL OHSR at Pavaratty- Work completed except flow meter. 5.50 LL OHSR at mullassery-work completed except flow meter. After the completion work of supplying laying of 300mm,250mm,200mm DIK9 pipe from Chattukulm to Pavaratty and Mullassery OHSR, these tanks can function . |
Nattika Project Dn AE 2 |
|
29 Apr 2024 |
6.70LL OHSR at Pavaratty- Work completed except flow meter. 5.50 LL OHSR at mullassery-work completed except flow meter. After the completion work of supplying laying of 300mm,250mm,200mm DIK9 pipe from Chattukulm to Pavaratty and Mullassery OHSR, these tanks can function . |
Nattika Project Dn AE 2 |
|
28 Apr 2024 |
6.70LL OHSR at Pavaratty- Work completed except flow meter. 5.50 LL OHSR at mullassery-work completed except flow meter. After the completion work of supplying laying of 300mm,250mm,200mm DIK9 pipe from Chattukulm to Pavaratty and Mullassery OHSR, these tanks can function . |
Nattika Project Dn AE 2 |
|
27 Apr 2024 |
6.70LL OHSR at Pavaratty- Work completed except flow meter. 5.50 LL OHSR at mullassery-work completed except flow meter. After the completion work of supplying laying of 300mm,250mm,200mm DIK9 pipe from Chattukulm to Pavaratty and Mullassery OHSR, these tanks can function . |
Nattika Project Dn AE 2 |
|
26 Apr 2024 |
6.70LL OHSR at Pavaratty- Work completed except flow meter. 5.50 LL OHSR at mullassery-work completed except flow meter. After the completion work of supplying laying of 300mm,250mm,200mm DIK9 pipe from Chattukulm to Pavaratty and Mullassery OHSR, these tanks can function . |
Nattika Project Dn AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
23/03/2019 |
Scheduled date of Completion of the Project |
22 Mar 2020 |
Expected date of Completion |
20/10/2022 |
Processing Dates
AS Date |
20 Aug 2018 |
TS Date |
20 Dec 2018 |