Project | DEPOSIT-Kochi Corporation-Laying 63mm PVC (6kg/cm2) pipe at A V John Alungal Byelane colony road in Division No28(old) 57(new) of Kochi Corporation |
---|---|
Project Code | EKMDEPO022314964P1 |
Type | Package |
Main Project | DEPOSIT-Kochi Corporation-Laying 63mm PVC (6kg/cm2) pipe at A V John Alungal Byelane colony road in Division No28(old) 57(new) of Kochi Corporation |
Funding Agency | DEPO |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | DEPOSIT-Kochi Corporation-Laying 63mm PVC (6kg/cm2) pipe at A V John Alungal Byelane colony road in Division No28(old) 57(new) of Kochi Corporation |
Status | On-going |
District | Ernakulam |
Executing Office | Vytilla Section 2 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 246000 |
TS Number | 5454/2023-2024 |
Technical specification | DEPOSIT-Kochi Corporation-Laying 63mm PVC (6kg/cm2) pipe at A V John Alungal Byelane colony road in Division No28(old) 57(new) of Kochi Corporation |
Contractor | K.B.Mukesh kumar (Mob: 9947426514) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 14/09/2023 |
---|---|
Scheduled date of Completion as per agreement | 13 Nov 2023 |
Expected date of Completion | 31/03/2024 |
TS Date | 07 Jun 2023 |
---|---|
Estimate Approval | 27 Feb 2023 |
NIT Approval | 14 Jun 2023 |
Tender Closing | 05 Jul 2023 |
Technichal Pre-Qualification | 05 Jul 2023 |
Price bid opening | 06 Jul 2023 |
Workorder Date | 04 Aug 2023 |
---|---|
NA | 17 Aug 2023 |
Vytilla Section AE - 2 |
Date: 23/03/2024 |
Work has been completed | 100% Completed
Ebill submitted.
Vytilla Section AE - 2 |
Date: 27/02/2024 |
Work in progress | 97% Completed
work completed. Ebill to be submitted..