DEPOSIT-Kochi Corporation-Laying 63mm PVC (6kg/cm2) pipe at A V John Alungal Byelane colony road in Division No28(old) 57(new) of Kochi Corporation

Project DEPOSIT-Kochi Corporation-Laying 63mm PVC (6kg/cm2) pipe at A V John Alungal Byelane colony road in Division No28(old) 57(new) of Kochi Corporation
Project Code EKMDEPO022314964P1
Type Package
Main Project DEPOSIT-Kochi Corporation-Laying 63mm PVC (6kg/cm2) pipe at A V John Alungal Byelane colony road in Division No28(old) 57(new) of Kochi Corporation
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Kochi Corporation-Laying 63mm PVC (6kg/cm2) pipe at A V John Alungal Byelane colony road in Division No28(old) 57(new) of Kochi Corporation
Status On-going
District Ernakulam
Executing Office Vytilla Section 2
Agreement Number
Agreement Date
TS Amount (Rs) 246000
TS Number 5454/2023-2024
Technical specification DEPOSIT-Kochi Corporation-Laying 63mm PVC (6kg/cm2) pipe at A V John Alungal Byelane colony road in Division No28(old) 57(new) of Kochi Corporation
Contractor K.B.Mukesh kumar (Mob: 9947426514)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 14/09/2023
Scheduled date of Completion as per agreement 13 Nov 2023
Expected date of Completion 31/03/2024

Processing Dates

TS Date 07 Jun 2023
Estimate Approval 27 Feb 2023
NIT Approval 14 Jun 2023
Tender Closing 05 Jul 2023
Technichal Pre-Qualification 05 Jul 2023
Price bid opening 06 Jul 2023

Approval Dates

Workorder Date 04 Aug 2023
NA 17 Aug 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Vytilla Section AE - 2
Date: 23/03/2024

Work has been completed | 100% Completed

Ebill submitted.

Vytilla Section AE - 2
Date: 27/02/2024

Work in progress | 97% Completed

work completed. Ebill to be submitted..