MLA -SDF 2020-21- Sri.Kovoor Kunjumon MLA-Kunnathoor LAC-RWSS to Sooranadu South - Replacing the damaged GI pipe from Yuvajana Vayanashala to Nandhanathu mukku in Ward No.IV in Sooranadu South Grama Panchayath

Project MLA -SDF 2020-21- Sri.Kovoor Kunjumon MLA-Kunnathoor LAC-RWSS to Sooranadu South - Replacing the damaged GI pipe from Yuvajana Vayanashala to Nandhanathu mukku in Ward No.IV in Sooranadu South Grama Panchayath
Project Code KLMGOK05203362P1
Type Package
Main Project MLA -SDF 2020-21- Sri.Kovoor Kunjumon MLA-Kunnathoor LAC-RWSS to Sooranadu South - Replacing the damaged GI pipe from Yuvajana Vayanashala to Nandhanathu mukku in Ward No.IV in Sooranadu South Grama Panchayath
Funding Agency GOK
Category MLA SDF
Type of scheme Water Supply
Scheme 4215-01-800-87
Description Pipe line extension by 110mm PVC pipe 6kg/cm2-490.0m, 90mm PVC pipe 6kg/cm2-295.0m
Status Completed
District Kollam
Executing Office Sasthamcottah WS Sn1
Agreement Number
Agreement Date
TS Amount (Rs)
TS Number
Technical specification 110mm PVC pipe 6kg/cm2-490.0m, 90mm PVC pipe 6kg/cm2-295.0m

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 06/10/2020
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion 10/10/2020

Processing Dates

AS Date 15 May 2020
TS Date 09 Jun 2020
Estimate Approval 09 Jun 2020
NIT Approval 17 Jun 2020
Tender Closing 25 Jul 2020
Price bid opening 28 Jul 2020

Approval Dates

Workorder Date 03 Aug 2020
NA 21 Aug 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam PH Dn EE
Date: 13/11/2021

Work has been completed | 100% Completed

Work has been completed and bill submitted. A bill of Rs. 4.13 Lakh has been claimed. .

Kollam PH Dn EE
Date: 06/07/2021

Work has been completed | 100% Completed

Work has been completed and bill submitted. A bill of Rs. 4.13 Lakh has been claimed..