Description |
Distribution pipe line 110mm PVC-800M, 90mm PVC-700M, 75mm PVC-350, 50mm PVC-350, 32mm PVC-150m and 25mm PVC-1300M
|
Status |
Completed |
District |
Kasaragod |
Executing Office |
Cheruvathoor Sn |
AS Amount (Rs) |
1810000
|
AS Number |
E1-5268/129 Dtd 2.6.2020 |
TS Amount (Rs) |
1800000 |
TS Number |
TS/2020-21/2019/10228 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
14 Jul 2022 |
Coverage |
Chemmakara, Nileshwar Muncipality |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work -Nileshwar Muncipality- Pipe line extension to to Chemmakara- Package |
Cheruvathoor Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
17 Oct 2022 |
final bill submitted |
Cheruvathur AE |
|
26 Sep 2022 |
final bill submitted |
Cheruvathur AE |
|
18 Aug 2022 |
completed |
Cheruvathur AE |
|
08 Aug 2022 |
completed |
Cheruvathur AE |
|
04 Aug 2022 |
completed |
Cheruvathur AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
29 Mar 2021 |
Expected date of Completion |
31/05/2022 |
Processing Dates
AS Date |
02 Jun 2020 |
TS Date |