DEPOSIT-KDP 2022-23 District Panchayath (WSS to Chavaramplavu )-Project no:38 – Extension of pipe line to Cherukathrapadi to kudilampadi and Cherukathrapadi to Muttathottathilpadi in Angadi Grama Panchayathu- Pipe line work.

Project DEPOSIT-KDP 2022-23 District Panchayath (WSS to Chavaramplavu )-Project no:38 – Extension of pipe line to Cherukathrapadi to kudilampadi and Cherukathrapadi to Muttathottathilpadi in Angadi Grama Panchayathu- Pipe line work.
Project Code PTADEPO032314019
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-KDP 2022-23 District Panchayath (WSS to Chavaramplavu )-Project no:38 – Extension of pipe line to Cherukathrapadi to kudilampadi and Cherukathrapadi to Muttathottathilpadi in Angadi Grama Panchayathu- Pipe line work.
Status Completed
District Pathanamthitta
Executing Office Ranni Sub Dn
AS Amount (Rs) 1541600
AS Number No.DBI-Price·:2022/2023(EST/4489/2023(DEPO)
TS Amount (Rs) 1540000
TS Number TS/4489/2023_26_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date 01 Oct 2023
Coverage DEPOSIT-KDP 2022-23 District Panchayath (WSS to Chavaramplavu )-Project no:38 – Extension of pipe line to Cherukathrapadi to kudilampadi and Cherukathrapadi to Muttathottathilpadi in Angadi Grama Panchayathu- Pipe line work.

Packages

No. Project Name Location View
1 DEPOSIT-KDP 2022-23 District Panchayath (WSS to Chavaramplavu )-Project no:38 – Extension of pipe line to Cherukathrapadi to kudilampadi and Cherukathrapadi to Muttathottathilpadi in Angadi Grama Panchayathu- Pipe line work. Ranni Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Oct 2023 Work completed Ranni PH Sn - AE
27 Apr 2023 Agreement Executed on 27/04/2023 Pathanamthitta PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 27/04/2023
Scheduled date of Completion of the Project 27 Apr 2023
Expected date of Completion 27/10/2023

Processing Dates

AS Date 03 Mar 2023
TS Date 14 Mar 2023

Other details

Project Officers View