- Home
- Deposit work of Thrikarpur Grama panchay...
Deposit work of Thrikarpur Grama panchayat-Pipeline extension towards Ayitti Vellapp road
Project |
Deposit work of Thrikarpur Grama panchayat-Pipeline extension towards Ayitti Vellapp road |
Project Code |
KGDDEPO07207194 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Pipeline extension |
Status |
Completed |
District |
Kasaragod |
Executing Office |
Cheruvathoor Sn |
AS Amount (Rs) |
1000000
|
AS Number |
DPC No.2170/2019-DPC/DPO/Ksd Dtd 02.7.2019 and 200/2020/DPC/DPO/Ksd Dtd 27.03.2020 |
TS Amount (Rs) |
1000000 |
TS Number |
TS/2020-2021/2018/12408 Dtd 19.10.2020 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
0.04 |
Actual Project Completion Date |
11 Mar 2022 |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work of Thrikarpur Grama panchayat-Pipeline extension towards Ayitti Vellapp road-Package |
Cheruvathoor Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
17 Oct 2022 |
completed |
Cheruvathur AE |
|
18 Aug 2022 |
completed |
Cheruvathur AE |
|
08 Aug 2022 |
completed |
Cheruvathur AE |
|
04 Aug 2022 |
completed |
Cheruvathur AE |
|
02 Aug 2022 |
completed |
Cheruvathur AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
05 Mar 2021 |
Expected date of Completion |
31/03/2022 |
Processing Dates
AS Date |
27 Mar 2020 |
TS Date |
19 Oct 2020 |