Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB- Design Construction and Commissioning of Water Supply Scheme to Zoological Park-Wild Life Conservation and Research centre at Puthur in Thrissur District

Project KIIFB- Design Construction and Commissioning of Water Supply Scheme to Zoological Park-Wild Life Conservation and Research centre at Puthur in Thrissur District
Project Code TCRGOK08185295
Type Main project
Funding Agency GOK
Category KIIFB
Type of scheme Water Supply
Scheme 2215-02-106-97
Description This scheme is sanctioned under KIIFB projects for providing a water supply scheme to the upcoming Zoological Park at Puthur in Thrissur District.Components are 6 M dia.Intake well, Pump house, 1.5 MLD water treatment plant,200 mm DI Raw water pumping main-4000M,100 mm DI clear water pumping main 225 M, Raw water pump sets (VT-discharge 18.75 lps, head 98 m),Clear water pumpsets, RCC sumps- 1LL and 6LL.
Status Completed
District Thrissur
Executing Office Peechi PH Sn
AS Amount (Rs) 1838200000
AS Number G.O9M.S)No.34/2018/F&WLD
TS Amount (Rs) 91000000
TS Number TS/2019-20/2018/14788
Total Bill Submitted (Rs) 42349450
Total Bill Paid (Rs) 42349450
Population Benefitted 5000
Capacity in MLD 1.50
Actual Project Completion Date 29 Mar 2021
Coverage Exclusively for the requirements of zoological park : Work Completed
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB- Design Construction and Commissioning of Water Supply Scheme to Zoological Park-Wild Life Conservation and Research centre at Puthur in Thrissur District Peechi PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Feb 2022 Work Completed Thrissur PH Dn EE
17 Dec 2021 10 LL OHSR roof slab completed including plastering work , Lamella clarifier completed including plastering. Construction of baffled flocculator completed including plastering, WTP structural work completed, 1 LL GLSR, 6LL GLSR completed including plastering. Raw water pumping main laying completed. Raw water pump sets erected , power connection obtained and trial running completed, Aluminum fabrication doors and windows work completed, pressure filter installation work completed, Landscape work completed, power connection obtained, WTP trial run completed, DLPC Period started. Peechi PH Sn - AE
28 Oct 2021 10 LL OHSR roof slab completed including plastering work , Lamella clarifier completed including plastering. Construction of baffled flocculator completed including plastering, WTP structural work completed, 1 LL GLSR, 6LL GLSR completed including plastering. Raw water pumping main laying completed. Raw water pump sets erected , power connection obtained and trial running completed, Aluminum fabrication doors and windows work completed, pressure filter installation work completed, Landscape work completed, power connection obtained, WTP trial run completed, DLPC Period started. Thrissur PH Dn EE
27 Aug 2021 10 LL OHSR roof slab completed including plastering work , Lamella clarifier completed including plastering. Construction of baffled flocculator completed including plastering, WTP structural work completed, 1 LL GLSR, 6LL GLSR completed including plastering. Raw water pumping main laying completed. Raw water pump sets erected , power connection obtained and trial running completed, Aluminum fabrication doors and windows work completed, pressure filter installation work completed, Landscape work completed, WTP ready for trial running, power connection not obtained. Thrissur PH Dn EE
17 Jul 2021 10 LL OHSR roof slab completed including plastering work , Lamella clarifier completed including plastering. Construction of baffled flocculator completed including plastering, WTP structural work completed, 1 LL GLSR, 6LL GLSR completed including plastering. Raw water pumping main laying completed. Raw water pump sets erected , power connection obtained and trial running completed, Aluminium fabrication doors and windows work in progress, pressure filter installation work in progress. Thrissur PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 20/02/2020
Scheduled date of Completion of the Project 31 May 2021
Expected date of Completion 31/01/2022

Processing Dates

AS Date 08 Aug 2018
TS Date 06 Jul 2019

Other details

Project Officers View