WSS to Mallappally, Anicadu & Kottangal panchayats - Phase 2 - Package 1

Project WSS to Mallappally, Anicadu & Kottangal panchayats - Phase 2 - Package 1
Project Code PTAGOK0317599P1
Type Package
Main Project WSS to Mallappally, Anicadu & Kottangal panchayats - Phase 2
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description This includes Supplying & Laying Raw Water and Clear Water Pumping Mains, Construction of intermediate storages
Status On-going
District Pathanamthitta
Executing Office Adoor Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 240000000
TS Number KWA/CE(SR)/05/201-18
Technical specification TS Issued
Contractor Abu Mathew (Mob: 9447037780)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
12 Jan 2022 Pending Pending Road Cut Related Risk An Amount of 3.54 Cr is submitted to FM for road restoration charges and amount not obtained and PWD not given Permission till date No comments available. Pending
01 Dec 2021 Pending Pending Road Cut Related Risk An Amountof 3.54 Cr is submitted to FM for road restoration charges and amount not obtained and PWD not given Permission No comments available. Pending
02 Aug 2021 Pending Pending Road Cut Related Risk An Amount of 3.54 Cr is Submitted to FM for road restoration charges and amount not obtained and PWD not given Permission till date No comments available. Pending
01 May 2021 Pending Pending Road Cut Related Risk An Amount of 3.54 Cr is Submitted to FM for road restoration charges and amount not obtained and PWD not given Permission till date No comments available. Pending
01 May 2021 Pending Pending Road Cut Related Risk An Amount of 3.54 Cr is Submitted to FM for road restoration charges and amount not obtained and PWD not given Permission till date No comments available. Pending
01 Apr 2021 Pending Pending Road Cut Related Risk An Amount of 3.54 Cr is Submitted to FM for road restoration charges and amount not obtained and PWD not given Permission till date No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/07/2019
Scheduled date of Completion as per agreement 30 Sep 2022
Expected date of Completion 31/12/2022

Processing Dates

TS Date 27 May 2017
Estimate Approval 15 Feb 2018
NIT Approval 27 Feb 2018
Tender Closing 31 Mar 2018
Technichal Pre-Qualification 02 Apr 2018
Price bid opening 03 Apr 2018

Approval Dates

Workorder Date 30 Aug 2018
NA 29 Dec 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Adoor Project Dn AE2
Date: 19/02/2024

Work in progress | 66% Completed

The work is terminated by Superintending Engineer vide order number SE/PHC/TVLA/2216/2017 vol III dated 27/09/2022.

Adoor Project Dn AE2
Date: 24/07/2023

Work in progress | 66% Completed

Work terminated by SE.