- Home
- DEPOSIT-2022/19270-Deposit work Thrikkak...
DEPOSIT-2022/19270-Deposit work Thrikkakara Municipality- Laying pipe laying at Annakkattu to Nilampathiniji Masjid road & VSNL Yuvadhara road in ward no 16 & 11 in Trikkakara Municipality-Pipeline Work
Project |
DEPOSIT-2022/19270-Deposit work Thrikkakara Municipality- Laying pipe laying at Annakkattu to Nilampathiniji Masjid road & VSNL Yuvadhara road in ward no 16 & 11 in Trikkakara Municipality-Pipeline Work |
Project Code |
EKMDEPO112213125 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
DEPOSIT-2022/19270-Deposit work Thrikkakara Municipality- Laying pipe laying at Annakkattu to Nilampathiniji Masjid road & VSNL Yuvadhara road in ward no 16 & 11 in Trikkakara Municipality-Pipeline Work |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Kochi WS Dn |
AS Amount (Rs) |
2740000
|
AS Number |
J2-20951/22 |
TS Amount (Rs) |
2730000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/7764/2022_26_1_1 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
150 |
Capacity in MLD |
0.75 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Annakkattu to Nilampathiniji Masjid road & VSNL Yuvadhara road in ward no 16 & 11 in Trikkakara Municipality |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT-2022/19270-Deposit work Thrikkakara Municipality- Laying pipe laying at Annakkattu to Nilampathiniji Masjid road & VSNL Yuvadhara road in ward no 16 & 11 in Trikkakara Municipality-Pipeline Work |
Trikkakara Sn |
|
2 |
DEPOSIT-2022/19270-Deposit work Thrikkakara Municipality- Laying pipe laying at Annakkattu to Nilampathiniji Masjid road & VSNL Yuvadhara road in ward no 16 & 11 in Trikkakara Municipality-Pipeline Work |
Trikkakara Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
19 Sep 2023 |
Bill Submitted to Subdivision. |
Thrikkakara Section AE |
|
18 Sep 2023 |
Bill Submitted to Subdivision. |
Thrikkakara Section AE |
|
15 Sep 2023 |
Bill Submitted to Subdivision. |
Thrikkakara Section AE |
|
13 Sep 2023 |
Bill Submitted to Subdivision. |
Thrikkakara Section AE |
|
11 Sep 2023 |
Bill Submitted to Subdivision. |
Thrikkakara Section AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
03/02/2023 |
Scheduled date of Completion of the Project |
26 Apr 2023 |
Expected date of Completion |
31/07/2023 |
Processing Dates
AS Date |
29 Nov 2022 |
TS Date |
09 Dec 2022 |