Jal Jeevan Mission- 2021-22- Providing Functional Household Tap Connections and allied works in Venganoor Panchayath- Phase III (Package 1)

Project Jal Jeevan Mission- 2021-22- Providing Functional Household Tap Connections and allied works in Venganoor Panchayath- Phase III (Package 1)
Project Code TVMJJM092112853
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission- 2021-22- Providing Functional Household Tap Connections and allied works in Venganoor Panchayath- Phase III (Package 1)
Status On-going
District Thiruvananthapuram
Executing Office Aralummoodu WS Sn
AS Amount (Rs) 116700000
AS Number 489/2021/WRD
TS Amount (Rs) 109200000
TS Number 10809/2022-2023
Total Bill Submitted (Rs) 62746000
Total Bill Paid (Rs) 62746000
Population Benefitted 3000
Capacity in MLD 0.30
Actual Project Completion Date Date is not specified
Coverage This work is included in Venganoor panchayath area.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM-2021-2022 - Providing Functional Household Tap Connections and allied works in Venganoor P anchayath (Phase 3 Package - 1) Aralummoodu WS Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 May 2024 Fifth & part bill submitted phase 3, package 1. 400 mm DI pipe laying at Vizhinjam Theatre junction. Aralumoodu AE
16 May 2024 Fifth & part bill submitted phase 3, package 1. 400 mm DI pipe laying at Vizhinjam Theatre junction. Aralumoodu AE
15 May 2024 Fifth & part bill submitted phase 3, package 1. 400 mm DI pipe laying at Vizhinjam Theatre junction. Aralumoodu AE
14 May 2024 Fifth & part bill submitted phase 3, package 1. 400 mm DI pipe laying at Vizhinjam Theatre junction. Aralumoodu AE
13 May 2024 Fifth & part bill submitted phase 3, package 1. 400 mm DI pipe laying at Vizhinjam Theatrejunction. Aralumoodu AE

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
03 Jul 2023 Pending Pending Natural Calamities Related Kalluvettankuzhi No comments available. Pending

Duration & Sanction dates

Date of start of Project 08/11/2022
Scheduled date of Completion of the Project 07 May 2023
Expected date of Completion 07/06/2023

Processing Dates

AS Date 18 Sep 2021
TS Date 19 Jul 2022

Other details

Project Officers View