DEPOSIT- Kodakara block panchayath -Construction of OHSR and laying pumping main at Eduthankunnu Mattathur Grammapanchayat-General Civil Work

Project DEPOSIT- Kodakara block panchayath -Construction of OHSR and laying pumping main at Eduthankunnu Mattathur Grammapanchayat-General Civil Work
Project Code TCRDEPO122213335
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Construction of OHSR and laying pumping main at Eduthankunnu Mattathur Grammapanchayat- General Civil Work
Status On-going
District Thrissur
Executing Office Chalakkudy PH Sn
AS Amount (Rs) 4200000
AS Number A2-600/22
TS Amount (Rs) 3900000
TS Number WRD/KWA-CE(CR)/E19-06-2023ST TS/8
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 5000
Capacity in MLD 0.10
Actual Project Completion Date Date is not specified
Coverage DEPOSIT- Kodakara block panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 DEPOSIT-Deposit work-Laying distribution line at Edathankunnu,Mattathur Grama panchayathLaying distribution line for Edthankunnu,Mattathur Panchayath-Pipeline Work Chalakkudy PH Sn
2 DEPOSIT- Kodakara block panchayath -Construction of OHSR and laying pumping main at Eduthankunnu Mattathur Grammapanchayat-General Civil Work Chalakkudy PH Sn
3 DEPOSIT-Laying pumping main at Edathankunnu-Laying pumping main at Edathankunnu,Mattathur panchayath-Pipeline Work Chalakkudy PH Sn
4 Deposit Work - Mattathur Grama Panchayath construction of OHSR and laying pumping main at Edathankunnu in Mattathur grama panchayath investigation ,Design and soil exploration Chalakkudy PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Jan 2024 Work in progress Chalakudy AE 1
08 Jan 2024 Work in progress Chalakudy AE 1
01 Jan 2024 Work in progress Chalakudy AE 1
27 Dec 2023 Work in progress Chalakudy AE 1
22 Dec 2023 concreting work completed Chalakudy AE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 10/04/2023
Scheduled date of Completion of the Project 31 Aug 2023
Expected date of Completion 15/03/2024

Processing Dates

AS Date 26 Dec 2022
TS Date 19 Jun 2023

Other details

Project Officers View