Deposit work of Thiruvananthapuram Corporation-Project no-S00548/22-Improving water supply by laying 63 mm PVC pipes in Charachira G Street near Charachira Devi temple in Nandhancode ward.

Project Deposit work of Thiruvananthapuram Corporation-Project no-S00548/22-Improving water supply by laying 63 mm PVC pipes in Charachira G Street near Charachira Devi temple in Nandhancode ward.
Project Code TVMDEPO03229576
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work of Thiruvananthapuram Corporation-Project no-S00548/22-Improving water supply by laying 63 mm PVC pipes in Charachira G Street near Charachira Devi temple in Nandhancode ward.
Status Completed
District Thiruvananthapuram
Executing Office Kowdiar WW North Sub Dn
AS Amount (Rs) 456000
AS Number J4/548/21
TS Amount (Rs) 456000
TS Number TS/2021-2022/2021/33797
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs)
Population Benefitted 100
Capacity in MLD 86.00
Actual Project Completion Date 04 Oct 2022
Coverage Charachira G Street near Charachira Devi temple in Nandhancode ward.

Packages

No. Project Name Location View
1 Deposit work of Thiruvananthapuram Corporation-Project no-S00548/22-Improving water supply by laying 63 mm PVC pipes in Charachira G Street near Charachira Devi temple in Nandhancode ward. Kowdiar Sn(Maintenance)

Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Oct 2022 work completed Thiruvananthapuram PH Dn (N) - EE
28 Sep 2022 work in progress. restoration pending Thiruvananthapuram PH Dn (N) - EE
06 Sep 2022 Work in progres Thiruvananthapuram PH Dn (N) - EE
02 Sep 2022 Work started Thiruvananthapuram PH Dn (N) - EE
26 Aug 2022 work started Thiruvananthapuram PH Dn (N) - EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/04/2022
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion 31/10/2022

Processing Dates

AS Date 24 Mar 2022
TS Date 25 Mar 2022

Other details

Project Officers View