Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission-2020-2021- Phase II-Providing FHTCs (90nos.) in Kozhinjampara Grama Panchayat

Project Jal Jeevan Mission-2020-2021- Phase II-Providing FHTCs (90nos.) in Kozhinjampara Grama Panchayat
Project Code PKDJJM10207734
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission-2020-2021- Phase II-Providing FHTCs (90nos.) in Kozhinjampara Grama Panchayat
Status Completed
District Palakkad
Executing Office Kozhinjampara PH Sn
AS Amount (Rs) 2520000
AS Number JJM DWSM
TS Amount (Rs) 1363000
TS Number TS/2020-21/2021/1865
Total Bill Submitted (Rs) 1430736
Total Bill Paid (Rs) 942516
Population Benefitted 375
Capacity in MLD 2.00
Actual Project Completion Date Date is not specified
Coverage Kozhinjampara
Implementation Schedule Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission-2020-2021- Phase II-Providing FHTCs (90nos.) in Kozhinjampara Grama Panchayat (Public tap, pipe line extension & enhancing the distribution system) Kozhinjampara PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Oct 2021 104 FHT connections were given and final bills submitted Kozhinjampara PH Sn AE
20 Sep 2021 1216.40 m of 63 mm PVC pipe and 298.50 m of 50mm GI pipes were laid and 104 nos FHTC given Kozhinjampara PH Sn AE
09 Sep 2021 1100 m of 63 mm PVC pipe and 210 m of 50mm GI pipes were laid and 76 nos FHTC given. Kozhinjampara PH Sn AE
31 Aug 2021 1000 m of 63 mm PVC pipe was laid and 46 FHTC given Kozhinjampara PH Sn AE
15 Jul 2021 Total 12 nos FHTC given Kozhinjampara PH Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 27/04/2021
Scheduled date of Completion of the Project 31 Aug 2021
Expected date of Completion 27/09/2021

Processing Dates

AS Date 27 Oct 2020
TS Date 06 Feb 2021

Other details

Project Officers View