Project | AMRUT 1.0 new -Fixing of new pump sets and laying of additional pumping line from WTP to tanker filling point and allied works |
---|---|
Project Code | EKMAMRUT122315630P1 |
Type | Package |
Main Project | AMRUT 1.0 new -Fixing of new pump sets and laying of additional pumping line from WTP to tanker filling point and allied works |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | AMRUT 1.0 new -Fixing of new pump sets and laying of additional pumping line from WTP to tanker filling point and allied works |
Status | On-going |
District | Ernakulam |
Executing Office | Vytilla Head works |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 4200000 |
TS Number | TS/24294/2023_5_1_1 Dated: 27-01-2024 |
Technical specification | AMRUT 1.0 new -Fixing of new pump sets and laying of additional pumping line from WTP to tanker filling point and allied works |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 17/02/2024 |
---|---|
Scheduled date of Completion as per agreement | 08 May 2024 |
Expected date of Completion | 08/05/2024 |
TS Date | 27 Jan 2024 |
---|---|
Estimate Approval | 24 Jan 2024 |
NIT Approval | 25 Jan 2024 |
Tender Closing | 08 Feb 2024 |
Technichal Pre-Qualification | 09 Feb 2024 |
Price bid opening | 09 Feb 2024 |
Workorder Date | 17 Feb 2024 |
---|---|
NA | 09 Feb 2024 |
Vytilla HW AE |
Date: 04/04/2024 |
Work in progress | 90% Completed
part bill submitted for an amt. of Rs.3311923.00.
Vytilla HW AE |
Date: 26/03/2024 |
Work in progress | 90% Completed
Work in progress.