REBUILD-Automation of Submersible pumps in Kerala Water Authority -implementation of Phase 1(Stage 1&2) part under Rebuilt Kerala Initiative -Surveilance mechanism for automated pumping stations at Kattampalli and Valpattanam-Supply andfixing of Surveillance mechanism for automated pumping stations at RWSS to Kattampalli and Valpattanam.

Project REBUILD-Automation of Submersible pumps in Kerala Water Authority -implementation of Phase 1(Stage 1&2) part under Rebuilt Kerala Initiative -Surveilance mechanism for automated pumping stations at Kattampalli and Valpattanam-Supply andfixing of Surveillance mechanism for automated pumping stations at RWSS to Kattampalli and Valpattanam.
Project Code KNRRKI042213255
Type Main project
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description Surveilance mechanism for automated pumping stations at Kattampalli and Valpattanam-Supply andfixing of Surveillance mechanism for automated pumping stations at RWSS to Kattampalli and Valpattanam.
Status Completed
District Kannur
Executing Office Kannur WS Sub Dn
AS Amount (Rs) 12440000
AS Number 6296/AE1/OPERATIONS)/2022/KWA
TS Amount (Rs) 40000
TS Number WRD/KWA-CE(NR)/EST_TS/4884/2022
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date 05 Jan 2023
Coverage

Packages

No. Project Name Location View
1 REBUILD-Automation of Submersible pumps in Kerala Water Authority -implementation of Phase 1(Stage 1&2) part under Rebuilt Kerala Initiative -Surveilance mechanism for automated pumping stations at Kattampalli and Valpattanam-Supply andfixing of Surveillance mechanism for automated pumping stations at RWSS to Kattampalli and Valpattanam. Kannur WS Sn 3

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Mar 2023 Work completed and bill submitted to Division office. Kannur WS Sub-Dn - AEE
25 Feb 2023 Completed Kannur PH Sn 3 AE
14 Feb 2023 installation completed Kannur PH Sn 3 AE
10 Feb 2023 installation completed Kannur PH Sn 3 AE
06 Feb 2023 site handover completed, work not started. Kannur PH Sn 3 AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 04 Apr 2022
TS Date 20 Dec 2022

Other details

Project Officers View