AMRUT 2.0 - Providing house connections and distribution network in Paravoor Municipality
Project |
AMRUT 2.0 - Providing house connections and distribution network in Paravoor Municipality |
Project Code |
KLMAMRUT112213227 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
works including JICA gap closing works , line extension and house connection works |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam Project Dn |
AS Amount (Rs) |
131580000
|
AS Number |
G.O.(Rt)No.2906/2022/LSGD |
TS Amount (Rs) |
128700000 |
TS Number |
ORDER No. WRD/KWA-CE(SR)/EST_TS/610/2022_26_1_1 Dated: 07-01-2023 |
Total Bill Submitted (Rs) |
34493475 |
Total Bill Paid (Rs) |
34493475 |
Population Benefitted |
49000 |
Capacity in MLD |
9.00 |
Actual Project Completion Date |
30 Sep 2024 |
Coverage |
entire Paravoor municipality |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT 2.0 - Providing house connections and distribution network in Paravoor Municipality |
Kollam Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
14 May 2024 |
25.5 km distribution completed out of 36.5 km and 1117 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed....Laying and FHTC work in progress...Geotagging and road restoration progress... |
Kollam Project HD |
|
13 May 2024 |
25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed....Interconnection work in progress...Laying and FHTC work in progress...Geotagging progress.. |
Kollam Project HD |
|
11 May 2024 |
25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed.....FHTC and Laying work in progress.. backfilling and Geotagging progress... |
Kollam Project HD |
|
10 May 2024 |
25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed.....FHTC and Laying work in progress.. backfilling and Geotagging progress... |
Kollam Project HD |
|
09 May 2024 |
25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Interconnection progress @ ward 5...FHTC and Laying work in progress..Geotagging progress... |
Kollam Project HD |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
31/01/2022 |
Scheduled date of Completion of the Project |
30 Sep 2024 |
Expected date of Completion |
21/12/2024 |
Processing Dates
AS Date |
24 Nov 2022 |
TS Date |
07 Jan 2023 |