Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT 2.0 - Providing house connections and distribution network in Paravoor Municipality

Project AMRUT 2.0 - Providing house connections and distribution network in Paravoor Municipality
Project Code KLMAMRUT112213227
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description works including JICA gap closing works , line extension and house connection works
Status On-going
District Kollam
Executing Office Kollam Project Dn
AS Amount (Rs) 131580000
AS Number G.O.(Rt)No.2906/2022/LSGD
TS Amount (Rs) 128700000
TS Number ORDER No. WRD/KWA-CE(SR)/EST_TS/610/2022_26_1_1 Dated: 07-01-2023
Total Bill Submitted (Rs) 34493475
Total Bill Paid (Rs) 34493475
Population Benefitted 49000
Capacity in MLD 9.00
Actual Project Completion Date 30 Sep 2024
Coverage entire Paravoor municipality

Packages

No. Project Name Location View
1 AMRUT 2.0 - Providing house connections and distribution network in Paravoor Municipality Kollam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 May 2024 25.5 km distribution completed out of 36.5 km and 1117 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed....Laying and FHTC work in progress...Geotagging and road restoration progress... Kollam Project HD
13 May 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed....Interconnection work in progress...Laying and FHTC work in progress...Geotagging progress.. Kollam Project HD
11 May 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed.....FHTC and Laying work in progress.. backfilling and Geotagging progress... Kollam Project HD
10 May 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed.....FHTC and Laying work in progress.. backfilling and Geotagging progress... Kollam Project HD
09 May 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Interconnection progress @ ward 5...FHTC and Laying work in progress..Geotagging progress... Kollam Project HD

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 31/01/2022
Scheduled date of Completion of the Project 30 Sep 2024
Expected date of Completion 21/12/2024

Processing Dates

AS Date 24 Nov 2022
TS Date 07 Jan 2023

Other details

Project Officers View