Jal Jeevan Mission (JJM)-JJM PORUVAZHY : PWD ROADRESTORATION SASTHAMNADA- CHAKUVALLY ROAD- SASTHAMNADA CHAKUVALLY ROAD Pipeline Work

Project Jal Jeevan Mission (JJM)-JJM PORUVAZHY : PWD ROADRESTORATION SASTHAMNADA- CHAKUVALLY ROAD- SASTHAMNADA CHAKUVALLY ROAD Pipeline Work
Project Code KLMJJM092115247
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-JJM PORUVAZHY : PWD ROADRESTORATION SASTHAMNADA- CHAKUVALLY ROAD- SASTHAMNADA CHAKUVALLY ROAD Pipeline Work
Status On-going
District Kollam
Executing Office Sasthamcottah WS sub Dn
AS Amount (Rs) 490600000
AS Number 489/2021/WRD
TS Amount (Rs) 1012239
TS Number 9034/2023-2024
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-JJM PORUVAZHY :PWD ROAD RESTORATIONSASTHAMNADA-CHAKUVALLY ROAD-SASTHAMNADA CHAKUVALLY ROADPipeline Work Sasthamcottah WS Sn2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 May 2024 work not yet started due to delay in getting PWD road cutting permission .Original period of completion expired on 05/12/23 .Demand notice received & forwarded to Division .Entered in PFMS seniority list & waiting for fund from head office. Sasthamcotta WS Sn 2 HW - AE
13 May 2024 work not yet started due to delay in getting PWD road cutting permission .Original period of completion expired on 05/12/23 .Demand notice received & forwarded to Division .Entered in PFMS seniority list & waiting for fund from head office. Sasthamcotta WS Sn 2 HW - AE
09 May 2024 work not yet started due to delay in getting PWD road cutting permission .Original period of completion expired on 05/12/23 .Demand notice received & forwarded to Division .Entered in PFMS seniority list & waiting for fund from head office. Sasthamcotta WS Sn 2 HW - AE
06 May 2024 work not yet started due to delay in getting PWD road cutting permission .Original period of completion expired on 05/12/23 .Demand notice received & forwarded to Division .Entered in PFMS seniority list & waiting for fund from head office. Sasthamcotta WS Sn 2 HW - AE
03 May 2024 work not yet started due to delay in getting PWD road cutting permission .Original period of completion expired on 05/12/23 .Demand notice received & forwarded to Division .Entered in PFMS seniority list & waiting for fund from head office. Sasthamcotta WS Sn 2 HW - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 18 Sep 2021
TS Date 15 Jul 2023

Other details

Project Officers View