JJM - Pariyaram Grama Panchayath (Appendix 7) - Providing FHTCs to Rural households , Retrofitting and Augmentation of Existing Rural Water Supply Schemes - 1258 nos

Project JJM - Pariyaram Grama Panchayath (Appendix 7) - Providing FHTCs to Rural households , Retrofitting and Augmentation of Existing Rural Water Supply Schemes - 1258 nos
Project Code TCRJJM07203868P1
Type Package
Main Project JJM - Pariyaram Grama Panchayath (Appendix 7) - Providing FHTCs to Rural households , Retrofitting and Augmentation of Existing Rural Water Supply Schemes
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description JJM - Pariyaram Grama Panchayath (Appendix 7) - Providing FHTCs to Rural households , Retrofitting and Augmentation of Existing Rural Water Supply Schemes - 1258 nos
Status On-going
District Thrissur
Executing Office Chalakkudy PH Sn II
Agreement Number
Agreement Date
TS Amount (Rs) 53100000
TS Number TS/2020-2021/2020/14405
Technical specification The proposal includes 1258 FHTCs.
Contractor Jyothi Constructions (Mob: 9447764227)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 21/11/2020
Scheduled date of Completion as per agreement 31 Mar 2022
Expected date of Completion 15/07/2022

Processing Dates

TS Date 11 Sep 2020
Estimate Approval 11 Sep 2020
NIT Approval 29 Aug 2020
Tender Closing 22 Sep 2020
Technichal Pre-Qualification 24 Sep 2020
Price bid opening 24 Sep 2020

Approval Dates

Workorder Date 09 Oct 2020
NA 27 Oct 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chalakudy AE 2
Date: 27/08/2022

Work has been completed | 100% Completed

Final bill under scrutiny will be submitted to DN office within a couple of days.

Chalakudy AE 2
Date: 25/08/2022

Work has been completed | 100% Completed

Final bill under scrutiny will be submitted to DN office within a couple of days.