REBUILD-IMPLEMENTATION OF RECOMMENDATION BY ENERGY MANAGEMENT CENTRE-KERALA-DEVELOPING SYSTEM FOR WASTE MANAGEMENT IN RECYCLING WASTE WATER AND REMOVE SLUDGE FROM 86 MLD WTP CHITHIRAKUNNU-ARUVIKKARA-GENERAL CIVIL WORK
Project |
REBUILD-IMPLEMENTATION OF RECOMMENDATION BY ENERGY MANAGEMENT CENTRE-KERALA-DEVELOPING SYSTEM FOR WASTE MANAGEMENT IN RECYCLING WASTE WATER AND REMOVE SLUDGE FROM 86 MLD WTP CHITHIRAKUNNU-ARUVIKKARA-GENERAL CIVIL WORK |
Project Code |
TVMRKI082212549 |
Type |
Main project |
Funding Agency |
RKI |
Category |
RKI |
Type of scheme |
Water Supply |
Scheme |
5475-00-115-94-05 |
Description |
REBUILD-IMPLEMENTATION OF RECOMMENDATION BY ENERGY MANAGEMENT CENTRE-KERALA-DEVELOPING SYSTEM FOR WASTE MANAGEMENT IN RECYCLING WASTE WATER AND REMOVE SLUDGE FROM 86 MLD WTP CHITHIRAKUNNU-ARUVIKKARA-GENERAL CIVIL WORK |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Aruvikkara Sn 5 |
AS Amount (Rs) |
10000000
|
AS Number |
KWA/JB/EW/EMC/EA/7813/2019 |
TS Amount (Rs) |
10000000 |
TS Number |
1195/2022-2023 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
|
Population Benefitted |
15000 |
Capacity in MLD |
86.00 |
Actual Project Completion Date |
30 Jan 2024 |
Coverage |
REBUILD-IMPLEMENTATION OF RECOMMENDATION BY ENERGY MANAGEMENT CENTRE-KERALA-DEVELOPING SYSTEM FOR WASTE MANAGEMENT IN RECYCLING WASTE WATER AND REMOVE SLUDGE FROM 86 MLD WTP CHITHIRAKUNNU-ARUVIKKARA-GENERAL CIVIL WORK |
Packages
No. |
Project Name |
Location |
View |
1 |
REBUILD-IMPLEMENTATION OF RECOMMENDATION BY ENERGY MANAGEMENT CENTRE-KERALA-DEVELOPING SYSTEM FOR WASTE MANAGEMENT IN RECYCLING WASTE WATER AND REMOVE SLUDGE FROM 86 MLD WTP CHITHIRAKUNNU-ARUVIKKARA-GENERAL CIVIL WORK |
Aruvikkara Sn 5 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
30 Jan 2024 |
The subject work is completed since the cost of the work exceeds the AS amount. |
Aruvikkara Sn 5 AE |
|
15 Jan 2024 |
RCC work for the foundation of the Recycling Settling tank was completed and RCC work for the wall was also completed.RCC works for retaining wall support completed.RCC works for the walkway slab completed.Interconnection works going on. |
Aruvikkara Sn 5 AE |
|
12 Jan 2024 |
RCC work for the foundation of the Recycling Settling tank was completed and RCC work for the wall was also completed. Additional RCC works for retaining wall support is going on |
Aruvikkara Sn 5 AE |
|
11 Jan 2024 |
RCC Work for wall is completed |
Aruvikkara Sn 5 AE |
|
05 Jan 2024 |
RCC work for foundation of Recycling Settling tank completed and RCC work for wall in progress |
Aruvikkara Sn 5 AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
02/12/2022 |
Scheduled date of Completion of the Project |
02 Jun 2023 |
Expected date of Completion |
31/12/2023 |
Processing Dates
AS Date |
16 Aug 2022 |
TS Date |
19 Sep 2022 |