Project | State plan-2017-18-Maintenance of IB at Aruvikkara |
---|---|
Project Code | TVMGOK07174734 |
Type | Main project |
Funding Agency | GOK |
Category | State plan |
Type of scheme | Water Supply |
Scheme | 2215-02-106-97 |
Description | State plan-2017-18-Maintenance of IB at Aruvikkara |
Status | Completed |
District | Thiruvananthapuram |
Executing Office | Aruvikkara WS Gen Sn |
AS Amount (Rs) | 1000000 |
AS Number | kwa |
TS Amount (Rs) | |
TS Number | |
Total Bill Submitted (Rs) | 1011077 |
Total Bill Paid (Rs) | |
Population Benefitted | |
Capacity in MLD | |
Actual Project Completion Date | 23 Aug 2018 |
Coverage |
Date of start of Project | 21/07/2018 |
---|---|
Scheduled date of Completion of the Project | Date is not specified |
Expected date of Completion | 23/08/2018 |
AS Date | 16 May 2018 |
---|---|
TS Date | 16 May 2018 |
Project Officers | View |
---|