JJM- nabl- accreditation - setting up of quality control subdistrict lab at sasthamcotta
Project |
JJM- nabl- accreditation - setting up of quality control subdistrict lab at sasthamcotta |
Project Code |
KLMJJM09218478 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Others |
Scheme |
4215-01-102-92-02 |
Description |
JJM- nabl- accreditation - setting up of quality control sub district lab at sasthamcotta |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam QC Sn |
AS Amount (Rs) |
11100000
|
AS Number |
GO(Rt) No. 489/2021/WRD |
TS Amount (Rs) |
3000000 |
TS Number |
TS/2021-2022/2021/29468 |
Total Bill Submitted (Rs) |
1843838 |
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
31 Mar 2022 |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
JJM- nabl- accreditation - setting up of quality control subdistrict lab at sasthamcotta |
Kollam QC Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
01 Sep 2022 |
Work completed |
Kollam QC AE |
|
17 Jun 2022 |
All work bacteriology and physical chemical area completed |
Kollam QC AE |
|
16 Apr 2022 |
Work Completed |
Kollam QC AE |
|
07 Apr 2022 |
Work completed almost just some minor finishing left |
Kollam QC AE |
|
18 Mar 2022 |
Titration table furniture fitting and final finishing in progress |
Kollam QC AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
21/11/2021 |
Scheduled date of Completion of the Project |
04 Feb 2022 |
Expected date of Completion |
Date is not specified |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
22 Oct 2021 |