Phase II-Providing Balance Distribution and FHTC Including LSGD Road Restoration Charges

Project Phase II-Providing Balance Distribution and FHTC Including LSGD Road Restoration Charges
Project Code MLPJJM08202868P2
Type Package
Main Project JJM WSS to Cheekode and Adjoining Villages- Providing FHTC toVazhayur Panchayath.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Phase II-Providing Balance Distribution and FHTC Including LSGD Road Restoration Charges
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 119600000
TS Number WRD/KWA-CE(NR)/EST_TS/3723/2023_26_3_2
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 25/05/2024
Scheduled date of Completion as per agreement 14 Nov 2024
Expected date of Completion 31/03/2025

Processing Dates

TS Date 17 Dec 2023
Tender Closing 16 Feb 2024
Price bid opening 17 Feb 2024

Approval Dates

Workorder Date 15 Mar 2024
NA 15 May 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malapuram Proj Dn AE 4
Date: 24/04/2026

Work in progress | 73% Completed

No work at site.Total as on today *Pvc 140 mm =0/24m. *Pvc 110 mm=0/60m. *pvc 90 mm=5297/5300mtr. *Pvc 63 mm=3400/3400mtr. Total pipe= 8670mtr. 80 mm GI= 454m . 50 mmGI= 686m. Connection details:- total conection as on today =1221/2750. Geotaged = 1216. Fhtc= 972. HTC = 244. Road restoration work :- Gsb 440m^3 Concrete 440m^3.

Malapuram Proj Dn AE 4
Date: 20/04/2026

Work in progress | 73% Completed

No work at site.Total as on today *Pvc 140 mm =0/24m. *Pvc 110 mm=0/60m. *pvc 90 mm=5297/5300mtr. *Pvc 63 mm=3400/3400mtr. Total pipe= 8670mtr. 80 mm GI= 454m . 50 mmGI= 686m. Connection details:- total conection as on today =1221/2750. Geotaged = 1216. Fhtc= 972. HTC = 244. Road restoration work :- Gsb 440m^3 Concrete 440m^3.