| Project | DRW 2022 -23 - Pipeline Replacement/Extension works-At Mambaram of Vengad panchayath-Pipeline Work |
|---|---|
| Project Code | KNRGOK102214307P1 |
| Type | Package |
| Main Project | DRW 2022 -23 - Pipeline Replacement/Extension works-At Mambaram of Vengad panchayath-Pipeline Work |
| Funding Agency | GOK |
| Category | DRW |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | DRW 2022 -23 - Pipeline Replacement/Extension works-At Mambaram of Vengad panchayath-Pipeline Work |
| Status | On-going |
| District | Kannur |
| Executing Office | Perlassery Sn 1 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 400000 |
| TS Number | 8549/2022-2023 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 16/12/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 22 Oct 2023 |
| Expected date of Completion | 03/05/2024 |
| TS Date | 16 Dec 2022 |
|---|---|
| Estimate Approval | 16 Dec 2022 |
| NIT Approval | 21 Dec 2022 |
| Tender Closing | 05 Jan 2023 |
| Technichal Pre-Qualification | 07 Jan 2023 |
| Price bid opening | 07 Jan 2023 |
| Workorder Date | 19 Jun 2023 |
|---|---|
| NA | 13 Jul 2023 |
| Perlasserry Sn 1 |
| Date: 16/10/2025 |
Work has been completed | 100% Completed
COMPLETED.
| Perlasserry Sn 1 |
| Date: 03/09/2024 |
Work has been completed | 100% Completed
Work completed on 19/08/2024.