AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Elayavoor Zone-Balance work-Elayavoor-Pipeline work

Project AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Elayavoor Zone-Balance work-Elayavoor-Pipeline work
Project Code KNRAMRUT122315863P1
Type Package
Main Project AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Elayavoor Zone-Balance work-Elayavoor-Pipeline work
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Elayavoor Zone-Balance work-Elayavoor-Pipeline work
Status On-going
District Kannur
Executing Office Kannur WS Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 25800000
TS Number 23561/2023-24
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 09/02/2024
Scheduled date of Completion as per agreement 29 Mar 2024
Expected date of Completion 30/11/2024

Processing Dates

TS Date 06 Jan 2024
NIT Approval 06 Jan 2024
Tender Closing 12 Jan 2024
Price bid opening 13 Jan 2024

Approval Dates

Workorder Date 27 Jan 2024
NA 31 Jan 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kannur WS Sn AE 2
Date: 05/12/2024

Work in progress | 98% Completed

Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable.

Kannur WS Sn AE 2
Date: 02/12/2024

Work in progress | 98% Completed

Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable.