Project | AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Elayavoor Zone-Balance work-Elayavoor-Pipeline work |
---|---|
Project Code | KNRAMRUT122315863P1 |
Type | Package |
Main Project | AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Elayavoor Zone-Balance work-Elayavoor-Pipeline work |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Elayavoor Zone-Balance work-Elayavoor-Pipeline work |
Status | On-going |
District | Kannur |
Executing Office | Kannur WS Sn 2 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 25800000 |
TS Number | 23561/2023-24 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 09/02/2024 |
---|---|
Scheduled date of Completion as per agreement | 29 Mar 2024 |
Expected date of Completion | 30/11/2024 |
TS Date | 06 Jan 2024 |
---|---|
NIT Approval | 06 Jan 2024 |
Tender Closing | 12 Jan 2024 |
Price bid opening | 13 Jan 2024 |
Workorder Date | 27 Jan 2024 |
---|---|
NA | 31 Jan 2024 |
Kannur WS Sn AE 2 |
Date: 05/12/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable.
Kannur WS Sn AE 2 |
Date: 02/12/2024 |
Work in progress | 98% Completed
Pipe laying and FHTC work Completed. Road restoration work will start at once the climate gets favorable.