WSS to Perinadu and Athikkayam Villages-Phase I- Remaining components

Project WSS to Perinadu and Athikkayam Villages-Phase I- Remaining components
Project Code PTAGOK1217608
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Renovation of existing well, pump house,collection chamber, construction of transformer room, supply of transformer, Construction of tanks at Pancharamukku, Chembanmudi etc.
Status On-going
District Pathanamthitta
Executing Office Adoor Project Dn
AS Amount (Rs) 33100000
AS Number G.O.(Rt) No. 1040/2017/WRD
TS Amount (Rs) 31110000
TS Number TS/2019-2020/2018/14016
Total Bill Submitted (Rs) 1987000
Total Bill Paid (Rs) 1
Population Benefitted 29973
Capacity in MLD 8.00
Actual Project Completion Date 31 May 2022
Coverage R- Perunad and Athikkayam villages
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 WSS to Perinadu and Athikkayam Villages-Phase I- Remaining components- Package I Adoor Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Aug 2022 GL tank at Chembanmudi, transformer room at intake well, collection chamber at intake and GLSR and pump house at Pancharamukku completed. All the Pump sets as per the schedule have been supplied and erected. Renovation of pump house at intake Perunad completed. Adoor Project Dn AE 4
15 Jun 2022 GL tank at Chembanmudi, transformer room at intake well, collection chamber at intake and GLSR and pump house at Pancharamukku completed. All the Pump sets as per the schedule have been supplied and erected except the raw water pump set. Renovation of pump house at intake Perunad is in progress. Adoor Project Dn AE 4
10 Jun 2022 GL tank at Chembanmudi, transformer room at intake well, collection chamber at intake and GLSR and pump house at Pancharamukku completed. All the Pump sets as per the schedule have been supplied and erected except the raw water pump set. Renovation of pump house at intake Perunad is in progress. Adoor Project Dn AE 4
03 Jun 2022 GL tank at Chembanmudi, transformer room at intake well, collection chamber at intake and GLSR and pump house at Pancharamukku completed. All the Pump sets as per the schedule have been supplied and erected except the raw water pump set. Renovation of pump house at intake Perunad is in progress. Adoor Project Dn AE 4
31 May 2022 GL tank at Chembanmudi, transformer room at intake well, collection chamber at intake and GLSR and pump house at Pancharamukku completed. All the Pump sets as per the schedule have been supplied and erected except the raw water pump set. Renovation of pump house at intake Perunad is in progress. Adoor Project Dn AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 20/01/2020
Scheduled date of Completion of the Project 20 Sep 2020
Expected date of Completion 30/11/2022

Processing Dates

AS Date 20 Dec 2017
TS Date 11 Jul 2019