Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

PACKAGE V-CONSTRUCTION OF 19 LL CAPACITY OHSR AT KAIVELIKKAL, LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN KUNNOTHUPARAMBA GRAMA PANCHAYATH

Project PACKAGE V-CONSTRUCTION OF 19 LL CAPACITY OHSR AT KAIVELIKKAL, LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN KUNNOTHUPARAMBA GRAMA PANCHAYATH
Project Code KNRJJM022213306P5
Type Package
Main Project JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Construction of 19 LL capacity OHSR at Kaivelikkal , Laying distribution system and providing FHTCs 7046nos
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 825700000
TS Number WRD/KWA-CE(NR)/EST_TS/5579/2022_26_1_1
Technical specification Construction of 19 LL capacity OHSR at Kaivelikkal , Laying distribution system and providing 7046 Nos FHTCs
Contractor M/S Kashmirilal Constructions Pvt.Limited (Mob: 9411113148)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 19/06/2023
Scheduled date of Completion as per agreement 19 Jun 2024
Expected date of Completion 31/03/2025

Processing Dates

TS Date 01 Nov 2022
Estimate Approval 01 Nov 2022
NIT Approval 02 Dec 2022
Tender Closing 17 Apr 2023
Technichal Pre-Qualification 02 Dec 2022
Price bid opening 19 Apr 2023

Approval Dates

Workorder Date 18 May 2023
NA 09 Jun 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 12/05/2025

Work in progress | 42% Completed

Earth excavation and PVC Pipe laying is in progress. Total quantity of pipe is 306.43 km,in that pipe supplied is 235.81 km. Out of this pipe laying of 136 km completed. 160 mm 10 kg PVC Laying is in progress at Nilangal - Kizhakkuvayal Road, 300 mm DI laying is in progress at Namathpalli-Nilangal Road.Construction of 19 LL OHSR started, columns earth excavation completed. house connnection and HTC work in progress, total 1250 nos. connection completed. .

Mattannur Project Sn 2 AE
Date: 03/05/2025

Work in progress | 41% Completed

Earth excavation and PVC Pipe laying is in progress. Total quantity of pipe is 306.43 km,in that pipe supplied is 235.81 km. Out of this pipe laying of 135 km completed. 160 mm 10 kg PVC Laying is in progress at Nilangal - Kizhakkuvayal Road, 200 mm DI laying is in progress at Kaivelikkal-Cheruvanchery-Muliyanthode Road. 19 LL OHSR earth excavation and set out work & marking for column pit completed. house connnection and HTC work in progress, total 1000nos. connection completed. Nilangal-Cherikkal PWD road restoration work in progress.