| Project | PACKAGE V-CONSTRUCTION OF 19 LL CAPACITY OHSR AT KAIVELIKKAL, LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN KUNNOTHUPARAMBA GRAMA PANCHAYATH |
|---|---|
| Project Code | KNRJJM022213306P5 |
| Type | Package |
| Main Project | JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Construction of 19 LL capacity OHSR at Kaivelikkal , Laying distribution system and providing FHTCs 7046nos |
| Status | On-going |
| District | Kannur |
| Executing Office | Mattannur Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 825700000 |
| TS Number | WRD/KWA-CE(NR)/EST_TS/5579/2022_26_1_1 |
| Technical specification | Construction of 19 LL capacity OHSR at Kaivelikkal , Laying distribution system and providing 7046 Nos FHTCs |
| Contractor | M/S Kashmirilal Constructions Pvt.Limited (Mob: 9411113148) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 19/06/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 19 Jun 2024 |
| Expected date of Completion | 31/03/2025 |
| TS Date | 01 Nov 2022 |
|---|---|
| Estimate Approval | 01 Nov 2022 |
| NIT Approval | 02 Dec 2022 |
| Tender Closing | 17 Apr 2023 |
| Technichal Pre-Qualification | 02 Dec 2022 |
| Price bid opening | 19 Apr 2023 |
| Workorder Date | 18 May 2023 |
|---|---|
| NA | 09 Jun 2023 |
| Mattannur Project Sn 2 AE |
| Date: 05/01/2026 |
Work in progress | 42% Completed
Total quantity of pipe is 306.43 km,in that pipe supplied is 235.81 km. Out of this, pipe laying of 140 km completed. Construction of 19 LL OHSR started, columns PCC completed.steel work for column RCC in progress. house connnection and HTC work in progress, Total 2200 nos. connection completed.11km LSGD road restoration completed..
| Mattannur Project Sn 2 AE |
| Date: 30/12/2025 |
Work in progress | 42% Completed
Total quantity of pipe is 306.43 km,in that pipe supplied is 235.81 km. Out of this, pipe laying of 140 km completed. Construction of 19 LL OHSR started, columns PCC completed.steel work for column RCC in progress. house connnection and HTC work in progress, Total 2100 nos. connection completed..