Deposit work :-Providing water supply service to various places (Mottekadu road,Kaloor -Kathrikkadavu road by lane ,Udaya Nagar,Kathrikkadavu -Pullepady road by lane)by supplying and laying 63/75/90 mm PVC 6 kg/cm2 in Division no:36 (old) of Kochi Corporation.

Project Deposit work :-Providing water supply service to various places (Mottekadu road,Kaloor -Kathrikkadavu road by lane ,Udaya Nagar,Kathrikkadavu -Pullepady road by lane)by supplying and laying 63/75/90 mm PVC 6 kg/cm2 in Division no:36 (old) of Kochi Corporation.
Project Code EKMDEPO11208805
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work :-Providing water supply service to various places (Mottekadu road,Kaloor -Kathrikkadavu road by lane ,Udaya Nagar,Kathrikkadavu -Pullepady road by lane)by supplying and laying 63/75/90 mm PVC 6 kg/cm2 in Division no:36 (old) of Kochi Corporation.
Status Completed
District Ernakulam
Executing Office Kaloor Sub Dn 2
AS Amount (Rs) 570000
AS Number On line fund transfer
TS Amount (Rs) 570000
TS Number TS/2020-2021/2020/11185
Total Bill Submitted (Rs) 434746
Total Bill Paid (Rs)
Population Benefitted 13148
Capacity in MLD 0.30
Actual Project Completion Date 31 May 2022
Coverage Deposit work :-Providing water supply service to various places (Mottekadu road,Kaloor -Kathrikkadavu road by lane ,Udaya Nagar,Kathrikkadavu -Pullepady road by lane)by supplying and laying 63/75/90 mm PVC 6 kg/cm2 in Division no:36 (old) of Kochi Corporation.

Packages

No. Project Name Location View
1 Deposit work :-Providing water supply service to various places (Mottekadu road,Kaloor -Kathrikkadavu road by lane ,Udaya Nagar,Kathrikkadavu -Pullepady road by lane)by supplying and laying 63/75/90 mm PVC 6 kg/cm2 in Division no:36 (old) of Kochi Corporation. Kaloor WW Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Apr 2024 Bill submitted Kaloor AE 2
19 Apr 2024 Bill submitted Kaloor AE 2
23 Mar 2024 Bill submitted Kaloor AE 2
06 Mar 2024 Bill submitted Kaloor AE 2
28 Feb 2024 Bill submitted Kaloor AE 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 28/06/2021
Scheduled date of Completion of the Project 28 Jul 2021
Expected date of Completion 31/03/2022

Processing Dates

AS Date 19 Nov 2020
TS Date 28 Dec 2020

Other details

Project Officers View