Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT-2.0 - WSS to Vatakara Municipality

Project AMRUT-2.0 - WSS to Vatakara Municipality
Project Code CLTAMRUT022314179
Type Main project
Funding Agency AMRUT
Category AMRUT 2
Type of scheme Water Supply
Scheme AMRUT
Description AMRUTH 2.0 - Water supply scheme to Vatakara Municipality— Rehabilitation of various components for improving water Supply to Vatakara Municipality
Status On-going
District Kozhikkode
Executing Office Vadakara WSP Sub Dn
AS Amount (Rs) 150270000
AS Number GO(Rt) No.473/2023/LSGD
TS Amount (Rs) 150270000
TS Number 2709/2023-2024
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 16000
Capacity in MLD 13.00
Actual Project Completion Date 31 Dec 2024
Coverage Vatakara Municipality
Work Plan Download

Packages

No. Project Name Location View
1 AMRUT-2.0 - WSS to Vadakara Municipality -Construction of 20 Lakh Litre Capacity OHSR at Puthiyappu, Rehabilitation of Existing Components, Extension of Pipelines and Providing FHTCs(PACKAGE - 2) Vadakara WSP Sn
2 AMRUT-2.0 - WSS to Vadakara Municipality -Design and Construction of 10 LL capacity OHSR at Veerancheri, Replacing Valves of Various Sizes in Distribution Line. Providing Online Boosting Arrangement for Paikkattumala, Replacing old and damaged AC pipes with PVC pipes of various sizes and Interconnection with branch lines(PACKAGE - 1) Vadakara WSP Sn
3 AMRUT-2.0 - WSS to Vadakara Municipality -Renovation of Existing 13 MLD Water Treatment plant at Kappumala.(PACKAGE - 4) Vadakara WSP Sn
4 AMRUT-2.0 - WSS to Vadakara Municipality - Supply, erection,testing and commissioning of 750 KVA Transformer at RWPH Koorangottukadavu(PACKAGE - 3) Vadakara WSP Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Oct 2023 veeranchery tank site clearance completed. pipe supply completed. puthiyapp tank and pipe line works agreement executed work not started, pipe not supplied. other components tender not finalised Vatakara PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 08/05/2023
Scheduled date of Completion of the Project 31 Dec 2025
Expected date of Completion 31/12/2025

Processing Dates

AS Date 23 Feb 2023
TS Date 08 May 2023

Other details

Project Officers View