Annual Planning Scheme:- 2020-21- Vadasserikkara Grama Panchaayth -extension of Pipe line from Kodinjiyil padi to Nochumannil to Ward No.3

Project Annual Planning Scheme:- 2020-21- Vadasserikkara Grama Panchaayth -extension of Pipe line from Kodinjiyil padi to Nochumannil to Ward No.3
Project Code PTADEPO01218968
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Annual Planning Scheme:- 2020-21- Vadasserikkara Grama Panchaayth -extension of Pipe line from Kodinjiyil padi to Nochumannil to Ward No.3
Status Completed
District Pathanamthitta
Executing Office Pathanamthitta PH Dn
AS Amount (Rs) 3792900
AS Number A2-432/20
TS Amount (Rs) 372000
TS Number TS/2021-22/2021/2816
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 250
Capacity in MLD 1.00
Actual Project Completion Date 22 Mar 2022
Coverage Kodinjiyil padi to Nochumannil to Ward No.3
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Annual Planning Scheme:- 2020-21- Vadasserikkara Grama Panchaayth -extension of Pipe line from Kodinjiyil padi to Nochumannil to Ward No.3 Vadasserikara Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Mar 2022 Work completed Pathanamthitta PH Dn EE
20 Feb 2022 Agreement Executed Pathanamthitta PH Dn EE
14 Feb 2022 Agreement executed Pathanamthitta PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 31/01/2022
Scheduled date of Completion of the Project 30 Apr 2022
Expected date of Completion 30/04/2022

Processing Dates

AS Date 06 Jan 2021
TS Date 24 Dec 2021

Other details

Project Officers View