AMRUT 2.0 -Providing sewerage lines in various areas for connecting lines already laid in AMRUT 1.0 in block L,J,K and I -Sewerage Work
Project |
AMRUT 2.0 -Providing sewerage lines in various areas for connecting lines already laid in AMRUT 1.0 in block L,J,K and I -Sewerage Work |
Project Code |
TVMAMRUT 2022314877 |
Type |
Main project |
Funding Agency |
AMRUT 2 |
Category |
AMRUT 2 |
Type of scheme |
Water Supply |
Scheme |
|
Description |
AMRUT 2.0 -Providing sewerage lines in various areas for connecting lines already laid in AMRUT 1.0 in block L,J,K and I -Sewerage Work
|
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Trivandrum Project Dn |
AS Amount (Rs) |
236700000
|
AS Number |
G.O.(Rt)No.431/2023/LSGD |
TS Amount (Rs) |
17860000 |
TS Number |
WRD/KWA-CE(SR)/EST_TS/6595/2023_27_1_1 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
|
Population Benefitted |
500 |
Capacity in MLD |
200.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
block L,J,K and I-towards Sreekaryam Area |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT 2.0- Branch Sewer from MH150 Ithadi towards sreekaryam areaPoviding 300mm RCC NP3 pipe sewer line from MH150 towards Sreekaryam area -Part 7-Sewerage Work |
Trivandrum Project Dn |
|
2 |
AMRUT 2.0- Branch Sewer from MH150 Ithadi towards Sreekaryam area- Providing 300mm RCC NP3 pipe sewer line from MH 150 towards Sreekaryam area Part 2-Sewerage Work |
Trivandrum Project Dn |
|
3 |
AMRUT 2.0- Branch Sewer from MH150 Ithadi towards Sreekaryam area- Providing 300mm RCC NP3 pipe sewer line from MH150 towards sreekaryam area - part3-Sewerage Work |
Trivandrum Project Dn |
|
4 |
AMRUT 2.0- Branch Sewer from MH150 Ithadi towards Sreekaryam area- Providing 300mm RCC NP3 pipe sewer line from MH150 towards sreekaryam area - part 4-Sewerage Work |
Trivandrum Project Dn |
|
5 |
AMRUT 2.0- Branch Sewer from MH150 Ithadi towards Sreekaryam area- Providing 300mm RCC NP3 pipe sewer line from MH 150 towards Sreekaryam area -part 5-Sewerage Work |
Trivandrum Project Dn |
|
6 |
AMRUT 2.0- Branch Sewer from MH150 Ithadi towards Sreekaryam area- Providing 300mm RCC NP3 pipe sewer line from MH150 towards Sreekaryam area -part6- Sewerage Work-1 |
Trivandrum Project Dn |
|
7 |
AMRUT 2.0 -Providing sewerage lines in various areas for connecting lines already laid in AMRUT 1.0 in blockL,J,K and I-Amruth 2. Branch sewer to Leksham veedu colony at Anayara-Pipeline Work |
Trivandrum Project Dn |
|
8 |
AMRUT 2.0 -Providing sewerage lines in various areas for connecting lines already laid in AMRUT 1.0 in block L,J,K and I-from Manchadi line RCC NP3 pipe sewer line to wards two branches such as near work shop(Part 1) Snehatheeram line No.1 - Pipeline Work |
Trivandrum Project Dn |
|
9 |
AMRUT 2.0 -Providing sewerage lines in various areas for connecting lines already laid in AMRUT 1.0 in block L,J,K and I-Laying RCC NP3 300mm sewer lines towards Sreekaryam Area - Part 1-Sewerage Work |
Trivandrum Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
06 May 2024 |
Lekshamveedu colony work completed. Snehatheeram part-1, Block L,J,K part 1,5,6,7 going on, Part 2,3,4 not started because pipe not supplied |
Thiruvananthapuram Project AE6 |
|
23 Apr 2024 |
Lekshamveedu colony work completed. Snehatheeram part-1, Block L,J,K part 1,5,6,7 going on, Part 2,3,4 not started because pipe not supplied |
Thiruvananthapuram Project AE6 |
|
15 Apr 2024 |
Lekshamveedu colony work completed. Snehatheeram part-1, Block L,J,K part 1,5,6,7 going on, Part 2,3,4 not started because pipe not supplied |
Thiruvananthapuram Project AE6 |
|
04 Apr 2024 |
Lekshamveedu colony work completed.
Snehatheeram part-1, Block L,J,K part 1,5,6,7 going on, Part 2,3,4 not started because pipe not supplied |
Thiruvananthapuram Project AE6 |
|
14 Mar 2024 |
snehatheeram part 1, sreekaryam part 1,5,6,7 work going on, lekshamveedu work completed |
Thiruvananthapuram Project AE6 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
Date is not specified |
Expected date of Completion |
30/11/2024 |
Processing Dates
AS Date |
19 Feb 2023 |
TS Date |
25 May 2023 |