Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission (JJM)-RWSS to Adat--5th SLSSC- PHASE III-RWSS to Adat-Laying additional branch pumping main (Hot Line) from Puzhakkal pumphouse to Over Head Tank at Chakkyamparambu- 100mm GI pipe(780m) - Part II-Working charges-Pipeline Work

Project Jal Jeevan Mission (JJM)-RWSS to Adat--5th SLSSC- PHASE III-RWSS to Adat-Laying additional branch pumping main (Hot Line) from Puzhakkal pumphouse to Over Head Tank at Chakkyamparambu- 100mm GI pipe(780m) - Part II-Working charges-Pipeline Work
Project Code TCRJJM052315290
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-RWSS to Adat--5th SLSSC- PHASE III-RWSS to Adat-Laying additional branch pumping main (Hot Line) from Puzhakkal pumphouse to Over Head Tank at Chakkyamparambu- 100mm GI pipe(780m) - Part II-Working charges-Pipeline Work
Status On-going
District Thrissur
Executing Office Thrissur WW Sn 2
AS Amount (Rs) 600000000
AS Number G.O.(Rt)No.401/2022/WRD
TS Amount (Rs) 1205000
TS Number WRD/KWA-CE(CR)/EST_TS/17098/2023_26_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
No Packages has been added for this project.

No status have been added to this project

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 10/11/2023
Scheduled date of Completion of the Project 09 May 2024
Expected date of Completion 09/05/2024

Processing Dates

AS Date 13 May 2022
TS Date 15 Jul 2023

Other details

Project Officers View