DEPOSIT KDP Ranni Block Panchayath 2022-23 Kochukalayil colony Ranni Division SC colony pipe line extension Project No 159/2023 Olivumala to Kochukalayil colony Ranni Gramapanchayath Ward 10

Project DEPOSIT KDP Ranni Block Panchayath 2022-23 Kochukalayil colony Ranni Division SC colony pipe line extension Project No 159/2023 Olivumala to Kochukalayil colony Ranni Gramapanchayath Ward 10
Project Code PTADEPO122214065
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT KDP Ranni Block Panchayath 2022-23 Kochukalayil colony Ranni Division SC colony pipe line extension Project No 159/2023 Olivumala to Kochukalayil colony Ranni Gramapanchayath Ward 10
Status On-going
District Pathanamthitta
Executing Office Ranni Sub Dn
AS Amount (Rs) 610000
AS Number A3-159/2022/Plan
TS Amount (Rs) 610000
TS Number TS/11544/2022_26_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage DEPOSIT KDP Ranni Block Panchayath 2022-23 Kochukalayil colony Ranni Division SC colony pipe line extension Project No 159/2023 Olivumala to Kochukalayil colony Ranni Gramapanchayath Ward 10

Packages

No. Project Name Location View
1 DEPOSIT KDP Ranni Block Panchayath 2022-23 Kochukalayil colony Ranni Division SC colony pipe line extension Project No 159/2023 Olivumala to Kochukalayil colony Ranni Gramapanchayath Ward 10 Ranni Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Feb 2024 Agreement executed on 10.05.2023 Ranni PH Sn - AE
03 Jan 2024 Agreement executed on 10.05.2023 Ranni PH Sn - AE
01 Jan 2024 Agreement executed on 10.05.2023 Ranni PH Sn - AE
30 Dec 2023 Agreement executed on 10.05.2023 Ranni PH Sn - AE
29 Dec 2023 Agreement executed on 10.05.2023 Ranni PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 10/05/2023
Scheduled date of Completion of the Project 10 Nov 2023
Expected date of Completion 10/11/2023

Processing Dates

AS Date 31 Dec 2022
TS Date 23 Jan 2023

Other details

Project Officers View