State Plan-2016-17-Guruvayoor drainage scheme, 1. Overhauling of mechanical, electricl instruments, Diesel Generators and transformers in 3MLD STP.
| Project |
State Plan-2016-17-Guruvayoor drainage scheme, 1. Overhauling of mechanical, electricl instruments, Diesel Generators and transformers in 3MLD STP. |
| Project Code |
TCRGOK11161780P5 |
| Type |
Package |
| Main Project |
State Plan-2016-17-Guruvayoor drainage scheme
|
| Funding Agency |
GOK |
| Category |
State plan |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-800-89 |
| Description |
State Plan-2016-17-Guruvayoor drainage scheme, 1. Overhauling of mechanical, electricl instruments, Diesel Generators and transformers in 3MLD STP. |
| Status |
On-going |
| District |
Thrissur |
| Executing Office |
Guruvayur PH Sn |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
9000000 |
| TS Number |
TS/2018-19/2019/1940 |
| Technical specification |
|
No project review have been added to this project
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
20/12/2016 |
| Scheduled date of Completion as per agreement |
Date is not specified |
| Expected date of Completion |
31/03/2021 |
Processing Dates
| TS Date |
11 Feb 2019 |
| Estimate Approval |
11 Feb 2019 |
Approval Dates
| Workorder Date |
08 Mar 2019 |
| NA |
09 Apr 2019 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Thrissur PH Dn EE |
| Date: 25/08/2021 |
Work has been completed | 100% Completed
Completed .
| Thrissur PH Dn EE |
| Date: 18/08/2021 |
Work has been completed | 100% Completed
Completed.