AMRUT SAAP 2016-17 WSS to Palakkad Municipality Phase II Package I - 600mm DI K9 New pumping main - From Malampuzha WTP to Mattumantha, Supply and erection of electromagnetic flow meter, Construction of 16LL OHSR at Kalmandapam

Project AMRUT SAAP 2016-17 WSS to Palakkad Municipality Phase II Package I - 600mm DI K9 New pumping main - From Malampuzha WTP to Mattumantha, Supply and erection of electromagnetic flow meter, Construction of 16LL OHSR at Kalmandapam
Project Code PKDAMRUT0817600
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description 600 mm DI CWPM to Mattumantha OHSR , 16 LL OHSR at Kalmandapam, Electromagnetic Flowmeter
Status Completed
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 97500000
AS Number GO(Rt) No.2800/2017/LSGD
TS Amount (Rs) 97500000
TS Number KWA/CE/NR/22/2017
Total Bill Submitted (Rs) 72346776
Total Bill Paid (Rs) 72346776
Population Benefitted 172683
Capacity in MLD 45.00
Actual Project Completion Date Date is not specified
Coverage Palakkad Municipality
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 AMRUT-2016-17- Palakkad WSS- Phase II-Package I: Construction of 16L LL OHSR at Kalmandapam Project Division Palakkad
2 AMRUT-2016-17- Palakkad WSS- Phase II-Package I: Providing new pipe line of 600mm DI K9 for CWPM from Malampuzha WTP to Mattumantha Project Division Palakkad
3 AMRUT 2016-17 Phase II-Package I Palakkad WSS - Supply and erection of electromagnetic flow meter. Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Nov 2020 Works completed Palakkad Project Dn AE 4
29 Sep 2020 600mm DI K9 Pumping main trial running in progress. Electromagnetic flowmeter supplied. 16 LL OHSR works completed. Palakkad Project Dn AE 4
14 Sep 2020 600mm DI K9 Pumping main trial running in progress. Electromagnetic flowmeter supplied. 16 LL OHSR works completed. Palakkad Project Dn AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 28/05/2018
Scheduled date of Completion of the Project 27 Nov 2019
Expected date of Completion 11/05/2020

Processing Dates

AS Date 15 Aug 2017
TS Date 17 Nov 2017

Other details