Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission - WSS to Manjoor Panchayath in Kottayam District -Supplying and Laying Casing MS pipe 500mm dia Across Railway Track at Kothanalloor Junction by Push through Method and Commissioning with FHTC in Manjoor Panchayath.

Project Jal Jeevan Mission - WSS to Manjoor Panchayath in Kottayam District -Supplying and Laying Casing MS pipe 500mm dia Across Railway Track at Kothanalloor Junction by Push through Method and Commissioning with FHTC in Manjoor Panchayath.
Project Code KTMJJM08202830
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Crossing Railway line by laying 300 mm MS pipe with 500mm MS Encasing pipe across Railway track at km 43/500-600 between Kuruppanthara (KRPP) and Ettumanoor (ETM), Interconnecting the newly laid lines with the existing, charging & commissioning of already laid distribution lines in zone II, rectifying the leakages if any occurs during charging and commissioning, Laying distribution lines in Zone I (balance portion) and providing FHTCs
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
AS Amount (Rs) 107500000
AS Number 541/2020/WRD
TS Amount (Rs) 20100000
TS Number 16796/2020-21
Total Bill Submitted (Rs) 37617051
Total Bill Paid (Rs) 37617051
Population Benefitted 29820
Capacity in MLD 25.00
Actual Project Completion Date 17 Sep 2021
Coverage Manjoor Panchayath 100%
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission - WSS to Manjoor Panchayath in Kottayam District -Supplying and Laying Casing MS pipe 500mm dia Across Railway Track at Kothanalloor Junction by Push through Method and Commissioning with FHTC in Manjoor Panchayath-Package 1 Kottayam Project Dn
2 JJM 2020-2021- WSS to Manjoor Panchayath in Kottayam District - Providing FHTCs in Manjoor Panchayatah on Quotation basis-Package 3 Kottayam Project Dn
3 JJM 2020-21 WSS to Manjoor Panchayath-laying pipe lines and providing FHTC in Manjoor Panchayath-Package 2 Kottayam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Oct 2022 JJM Review Meeting was conducted on 7-10-22 at Manjoor Panchayath Office by Executive Engineer, Project Division, Kottayam Kottayam AE 3
04 Aug 2022 WSS to Manjoor Panchayath Pacakge 2 -Letter given to Manjoor Panchayath regarding release request letter from Contractor Kottayam AE 3
04 Feb 2022 Interconnection work at Kothanelloor Junction in Ettumanoor Ernakulam road completed . Valve chamber cover slab concreting work progressing at Chamakkala side of Railway line Kottayam AE 3
07 Jan 2022 Honourable MP Thomas Chazhikkadan, EE, AXE and AE visited the site on 05/01/202 to review progress of the work Kottayam AE 3
08 Nov 2021 In Package 1- Work schedule submitted to Senior section Engineer ,Southern Railway to get the approval for execution of work.Materials supplied at site.PWD road cutting sanction pending for 2 reaches. In Package 2-1105 FHTCs provided out of 6155 FHTCs and 1.4km pipe laid out of 6km.PWD sanction pending for four reaches. In Package 3-1000 FHTCs given on quotation basis Kottayam AE 3

Project Review

See All Review messages
Review Date Review Message Review Attended By
25 Jun 2021 Add dated photographs showing progress of the work EE AEE AE

Duration & Sanction dates

Date of start of Project 04/11/2020
Scheduled date of Completion of the Project 22 Aug 2021
Expected date of Completion 30/11/2022

Processing Dates

AS Date 21 Aug 2020
TS Date 12 Feb 2021

Other details

Project Officers View