Jal Jeevan Mission - WSS to Manjoor Panchayath in Kottayam District -Supplying and Laying Casing MS pipe 500mm dia Across Railway Track at Kothanalloor Junction by Push through Method and Commissioning with FHTC in Manjoor Panchayath.
Project |
Jal Jeevan Mission - WSS to Manjoor Panchayath in Kottayam District -Supplying and Laying Casing MS pipe 500mm dia Across Railway Track at Kothanalloor Junction by Push through Method and Commissioning with FHTC in Manjoor Panchayath. |
Project Code |
KTMJJM08202830 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Crossing Railway line by laying 300 mm MS pipe with 500mm MS Encasing pipe across Railway track at km 43/500-600 between Kuruppanthara (KRPP) and Ettumanoor (ETM), Interconnecting the newly laid lines with the existing, charging & commissioning of already laid distribution lines in zone II, rectifying the leakages if any occurs during charging and commissioning, Laying distribution lines in Zone I (balance portion) and providing FHTCs |
Status |
On-going |
District |
Kottayam |
Executing Office |
Kottayam Project Dn |
AS Amount (Rs) |
107500000
|
AS Number |
541/2020/WRD |
TS Amount (Rs) |
20100000 |
TS Number |
16796/2020-21 |
Total Bill Submitted (Rs) |
37617051 |
Total Bill Paid (Rs) |
37617051 |
Population Benefitted |
29820 |
Capacity in MLD |
25.00 |
Actual Project Completion Date |
17 Sep 2021 |
Coverage |
Manjoor Panchayath 100% |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission - WSS to Manjoor Panchayath in Kottayam District -Supplying and Laying Casing MS pipe 500mm dia Across Railway Track at Kothanalloor Junction by Push through Method and Commissioning with FHTC in Manjoor Panchayath-Package 1 |
Kottayam Project Dn |
|
2 |
JJM 2020-2021- WSS to Manjoor Panchayath in Kottayam District - Providing FHTCs in Manjoor Panchayatah on Quotation basis-Package 3 |
Kottayam Project Dn |
|
3 |
JJM 2020-21 WSS to Manjoor Panchayath-laying pipe lines and providing FHTC in Manjoor Panchayath-Package 2 |
Kottayam Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
07 Oct 2022 |
JJM Review Meeting was conducted on 7-10-22 at Manjoor Panchayath Office by Executive Engineer, Project Division, Kottayam |
Kottayam AE 3 |
|
04 Aug 2022 |
WSS to Manjoor Panchayath Pacakge 2 -Letter given to Manjoor Panchayath regarding release request letter from Contractor |
Kottayam AE 3 |
|
04 Feb 2022 |
Interconnection work at Kothanelloor Junction in Ettumanoor Ernakulam road completed .
Valve chamber cover slab concreting work progressing at Chamakkala side of Railway line |
Kottayam AE 3 |
|
07 Jan 2022 |
Honourable MP Thomas Chazhikkadan, EE, AXE and AE visited the site on 05/01/202 to review progress of the work |
Kottayam AE 3 |
|
08 Nov 2021 |
In Package 1- Work schedule submitted to Senior section Engineer ,Southern Railway to get the approval for execution of work.Materials supplied at site.PWD road cutting sanction pending for 2 reaches. In Package 2-1105 FHTCs provided out of 6155 FHTCs and 1.4km pipe laid out of 6km.PWD sanction pending for four reaches. In Package 3-1000 FHTCs given on quotation basis |
Kottayam AE 3 |
|
Review Date |
Review Message |
Review Attended By |
25 Jun 2021 |
Add dated photographs showing progress of the work |
EE AEE AE |
Duration & Sanction dates
Date of start of Project |
04/11/2020 |
Scheduled date of Completion of the Project |
22 Aug 2021 |
Expected date of Completion |
30/11/2022 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
12 Feb 2021 |