Project | DEPOSIT WORK :- KRISHNAPURAM GRAMAPANCHAYAT - 2020 - 2021 PROJECT NUMBER 66/21- PIPE LINE EXTENSION OF 90 MM PVC PIPE LINE FROM PALLETHU - ALUMOOTIL ROAD AND HEALTH CENTER THOTTETHEKKADATHU ROAD IN WARD NO.06 OF KRISHNAPURAM PANCHAYAT. |
---|---|
Project Code | ALPDEPO032211956P1 |
Type | Package |
Main Project | DEPOSIT WORK :- KRISHNAPURAM GRAMAPANCHAYAT - 2020 - 2021 PROJECT NUMBER 66/21- PIPE LINE EXTENSION OF 90 MM PVC PIPE LINE FROM PALLETHU - ALUMOOTIL ROAD AND HEALTH CENTER THOTTETHEKKADATHU ROAD IN WARD NO.06 OF KRISHNAPURAM PANCHAYAT. |
Funding Agency | DEPO |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | Estimate prepared as per Lt No. K 3. 6215(1)/2020 dated 05/08/2020 of the Secretary, Krishnapuram GramaPanchayat for pipe line extension work from Pallethu - Alummoottil road and Health center - Thottethekkadathu Road in Ward No. 6 of Krishnapuram Grama Panchayat. It is hydraulically feasible at present stage |
Status | On-going |
District | Alappuzha |
Executing Office | Kayamkulam PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 99000 |
TS Number | ORDER No. TS/2021-2022/2020/25557 Dated: 21-03-2022 |
Technical specification | Estimate prepared as per Lt No. K 3. 6215(1)/2020 dated 05/08/2020 of the Secretary, Krishnapuram GramaPanchayat for pipe line extension work from Pallethu - Alummoottil road and Health center - Thottethekkadathu Road in Ward No. 6 of Krishnapuram Grama Panchayat. It is hydraulically feasible at present stage |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 10/08/2022 |
---|---|
Scheduled date of Completion as per agreement | 09 Sep 2022 |
Expected date of Completion | 09/09/2022 |
TS Date | 21 Mar 2022 |
---|---|
Estimate Approval | 21 Mar 2022 |
NIT Approval | 22 Mar 2022 |
Tender Closing | 05 Apr 2022 |
Technichal Pre-Qualification | 08 Apr 2022 |
Price bid opening | 08 Apr 2022 |
Workorder Date | 11 Jul 2022 |
---|---|
NA | 10 Aug 2022 |
Kayamkulam AE |
Date: 11/03/2024 |
Work has started | 0% Completed
Non starter.
Kayamkulam AE |
Date: 04/03/2024 |
Work has started | 0% Completed
Non starter.