- Home
- RKI-Energy Optimationand replacing in Ef...
RKI-Energy Optimationand replacing in Efficient pumping system In HT Connections.
Project |
RKI-Energy Optimationand replacing in Efficient pumping system In HT Connections. |
Project Code |
TVMRKI082213468 |
Type |
Main project |
Funding Agency |
RKI |
Category |
RKI |
Type of scheme |
Water Supply |
Scheme |
5475-00-115-94-05 |
Description |
RKI-Energy Optimationand replacing in Efficient pumping system In HT Connections.TSS.107 MLD STP Muttathara,Tvpm.Supply ,instalation,Testing and commissioning of a new 11KV HT outdoor type cubicle asper KSEB standards for reducing contract demand from 1250 KVA to 1100 KVA. |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Muttathara STP Sn |
AS Amount (Rs) |
230100
|
AS Number |
GO Rt No.299/2022/P&EA dtd. 02.08.2022 of GOK |
TS Amount (Rs) |
230100 |
TS Number |
TS /2022-2023/4118 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
500000 |
Capacity in MLD |
107.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Muttathara STP |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
RKI-Energy Optimationand replacing in Efficient pumping system In HT Connections.TSS.107 MLD STP Muttathara,Tvpm.Supply ,instalation,Testing and commissioning of a new 11KV HT outdoor type cubicle asper KSEB standards for reducing contract demand from 1250 KVA to 1100 KVA. |
Kuriathy Sewerage Sn 3 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
20 Dec 2023 |
Approval for fixing CT-PT unit obtained from TMR, the work was planned on 10/11/2023. But the alternator part of DG set for Inlet well at STP became faulty. Hence shut down could not be effected. The maintenance of DG set is progressing. Installation can be planned afterwards. The issue has been communicated with TMR. |
Muttathara STP AE |
|
01 Dec 2023 |
Approval for fixing CT-PT unit obtained from TMR, the work was planned on 10/11/2023. But the alternator part of DG set for Inlet well at STP became faulty. Hence shut down could not be effected. The maintenance of DG set is progressing. Installation can be planned afterwards. |
Muttathara STP AE |
|
14 Nov 2023 |
Approval for fixing CT-PT unit obtained from TMR, the work was planned on 10/11/2023. But the alternator part of DG set for Inlet well at STP became faulty. Hence shut down could not be effected. The maintenance of DG set is progressing. Installation can be planned afterwards. |
Muttathara STP AE |
|
18 Sep 2023 |
CT-PT unit submitted to TMR by the contractor for testing and approval, letter submitted to SE, KSEB. Work in progress. Procedure for demand deduction in progress. |
Muttathara STP AE |
|
18 Aug 2023 |
CT-PT unit submitted to TMR by the contractor for testing and approval, letter submitted to SE, KSEB. Work in progress. Procedure for demand deduction in progress. |
Muttathara STP AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
19/10/2022 |
Scheduled date of Completion of the Project |
19 Feb 2023 |
Expected date of Completion |
15/06/2023 |
Processing Dates
AS Date |
02 Aug 2022 |
TS Date |
03 Aug 2022 |