Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of 14 Nos Vertical Turbine pump sets at Various pump houses Under P.H.Section Angamaly.

Project Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of 14 Nos Vertical Turbine pump sets at Various pump houses Under P.H.Section Angamaly.
Project Code EKMRKI042211850P2
Type Package
Main Project Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of pumping stations
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of 14 Nos Vertical Turbine pump sets at Various pump houses Under P.H.Section Angamaly.
Status On-going
District Ernakulam
Executing Office Angamaly Sn
Agreement Number
Agreement Date
TS Amount (Rs) 2100000
TS Number TS/2022-2023/2022/25305 Dated: 25-07-2022
Technical specification NIL
Contractor M/s POTTS DEVICES AND SYSTEMS (Mob: 9207742587)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 06/08/2022
Scheduled date of Completion as per agreement 22 Sep 2022
Expected date of Completion 15/03/2023

Processing Dates

TS Date 25 Jul 2022
Estimate Approval 25 Jul 2022
NIT Approval 25 Jul 2022
Tender Closing 04 Aug 2022
Technichal Pre-Qualification 25 Jul 2022
Price bid opening 08 Aug 2022

Approval Dates

Workorder Date 06 Aug 2022
NA 17 Aug 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Angamaly AEE
Date: 17/05/2023

Work has been completed | 100% Completed

Work has been completed.

Angamaly AEE
Date: 12/05/2023

Work has been completed | 100% Completed

Work has been completed.