Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Flood Relief Work:2018-WSS to Arayanjilimon ward of Perunadu panchayath

Project Flood Relief Work:2018-WSS to Arayanjilimon ward of Perunadu panchayath
Project Code PTAGOK0919609
Type Main project
Funding Agency GOK
Category Flood Works
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Flood Relief Work:2018- Restoration of water supply in Arayanjilimon ward of Perunadu panchayath- Construction of GLSR at Perunkavumala, laying 100 mm DI gravity main to Arayanjilimon and Perunkavumala, replacing damaged distribution lines and supply and erection of C/W pumpset at Venkurinji and Olikkal sump.
Status Completed
District Pathanamthitta
Executing Office Adoor Project Dn
AS Amount (Rs) 50000000
AS Number KWA/HO/OP-III/625/2018
TS Amount (Rs) 31110000
TS Number TS/2019-2020/2018/15349
Total Bill Submitted (Rs) 6765230
Total Bill Paid (Rs) 6765230
Population Benefitted 1100
Capacity in MLD 0.25
Actual Project Completion Date 31 Mar 2022
Coverage Arayanjilimon ward of Perunadu panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Flood Relief Work:2018-WSS to Arayanjilimon ward of Perunadu panchayath- Package I Adoor Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Apr 2022 Completed works on 31.3.2022 Adoor Project Dn AE 4
10 Apr 2022 Completed works Adoor Project Dn AE 4
07 Apr 2022 Supplied 6600 m of 100 mm DI K9 pipe, 400 m of 150mm DI K9 pipe, 1000 m of 80 mm GI(M) pipe, 1250 m of 100 mm GI(M) pipe, 3060 m of 90 mm PVC 10 kg pipe and 3060 m of 110 mm PVC 10 kg pipe............ Laid 6600 m of 100 mm DI K9 pipe, 400 m of 150mm DI K9 pipe, 1000 m of 80 mm GI(M) pipe, 1250 m of 100 mm GI(M) pipe, 3045 m of 90 mm PVC 10 kg pipe and 3060 m of 110 mm PVC 10 kg pipe. Laying work and interconnection works are almost completed, balance work is in progress. GLSR at Arayanjalimon-Perunkavumala completed Adoor Project Dn AE 4
06 Apr 2022 Supplied 6600 m of 100 mm DI K9 pipe, 400 m of 150mm DI K9 pipe, 1000 m of 80 mm GI(M) pipe, 1250 m of 100 mm GI(M) pipe, 3060 m of 90 mm PVC 10 kg pipe and 3060 m of 110 mm PVC 10 kg pipe............ Laid 6600 m of 100 mm DI K9 pipe, 400 m of 150mm DI K9 pipe, 1000 m of 80 mm GI(M) pipe, 1250 m of 100 mm GI(M) pipe, 3045 m of 90 mm PVC 10 kg pipe and 3060 m of 110 mm PVC 10 kg pipe. Laying work and interconnection works are almost completed, balance work is in progress. GLSR at Arayanjalimon-Perunkavumala completed Adoor Project Dn AE 4
04 Apr 2022 Supplied 6600 m of 100 mm DI K9 pipe, 400 m of 150mm DI K9 pipe, 1000 m of 80 mm GI(M) pipe, 1250 m of 100 mm GI(M) pipe, 3060 m of 90 mm PVC 10 kg pipe and 3060 m of 110 mm PVC 10 kg pipe............ Laid 6600 m of 100 mm DI K9 pipe, 400 m of 150mm DI K9 pipe, 1000 m of 80 mm GI(M) pipe, 1250 m of 100 mm GI(M) pipe, 3045 m of 90 mm PVC 10 kg pipe and 3060 m of 110 mm PVC 10 kg pipe. Laying work and interconnection works are almost completed, balance work is in progress. GLSR at Arayanjalimon-Perunkavumala completed Adoor Project Dn AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 08/06/2020
Scheduled date of Completion of the Project 31 Mar 2022
Expected date of Completion 31/03/2022

Processing Dates

AS Date 17 Jan 2019
TS Date 23 Jan 2020

Other details

Project Officers View