Flood Relief Work:2018-WSS to Arayanjilimon ward of Perunadu panchayath
Project |
Flood Relief Work:2018-WSS to Arayanjilimon ward of Perunadu panchayath |
Project Code |
PTAGOK0919609 |
Type |
Main project |
Funding Agency |
GOK |
Category |
Flood Works |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Flood Relief Work:2018- Restoration of water supply in Arayanjilimon ward of Perunadu panchayath- Construction of GLSR at Perunkavumala, laying 100 mm DI gravity main to Arayanjilimon and Perunkavumala, replacing damaged distribution lines and supply and erection of C/W pumpset at Venkurinji and Olikkal sump. |
Status |
Completed |
District |
Pathanamthitta |
Executing Office |
Adoor Project Dn |
AS Amount (Rs) |
50000000
|
AS Number |
KWA/HO/OP-III/625/2018 |
TS Amount (Rs) |
31110000 |
TS Number |
TS/2019-2020/2018/15349 |
Total Bill Submitted (Rs) |
6765230 |
Total Bill Paid (Rs) |
6765230 |
Population Benefitted |
1100 |
Capacity in MLD |
0.25 |
Actual Project Completion Date |
31 Mar 2022 |
Coverage |
Arayanjilimon ward of Perunadu panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Flood Relief Work:2018-WSS to Arayanjilimon ward of Perunadu panchayath- Package I |
Adoor Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
10 Apr 2022 |
Completed works on 31.3.2022 |
Adoor Project Dn AE 4 |
|
10 Apr 2022 |
Completed works |
Adoor Project Dn AE 4 |
|
07 Apr 2022 |
Supplied 6600 m of 100 mm DI K9 pipe, 400 m of 150mm DI K9 pipe, 1000 m of 80 mm GI(M) pipe, 1250 m of 100 mm GI(M) pipe, 3060 m of 90 mm PVC 10 kg pipe and 3060 m of 110 mm PVC 10 kg pipe............ Laid 6600 m of 100 mm DI K9 pipe, 400 m of 150mm DI K9 pipe, 1000 m of 80 mm GI(M) pipe, 1250 m of 100 mm GI(M) pipe, 3045 m of 90 mm PVC 10 kg pipe and 3060 m of 110 mm PVC 10 kg pipe. Laying work and interconnection works are almost completed, balance work is in progress. GLSR at Arayanjalimon-Perunkavumala completed |
Adoor Project Dn AE 4 |
|
06 Apr 2022 |
Supplied 6600 m of 100 mm DI K9 pipe, 400 m of 150mm DI K9 pipe, 1000 m of 80 mm GI(M) pipe, 1250 m of 100 mm GI(M) pipe, 3060 m of 90 mm PVC 10 kg pipe and 3060 m of 110 mm PVC 10 kg pipe............ Laid 6600 m of 100 mm DI K9 pipe, 400 m of 150mm DI K9 pipe, 1000 m of 80 mm GI(M) pipe, 1250 m of 100 mm GI(M) pipe, 3045 m of 90 mm PVC 10 kg pipe and 3060 m of 110 mm PVC 10 kg pipe. Laying work and interconnection works are almost completed, balance work is in progress. GLSR at Arayanjalimon-Perunkavumala completed |
Adoor Project Dn AE 4 |
|
04 Apr 2022 |
Supplied 6600 m of 100 mm DI K9 pipe, 400 m of 150mm DI K9 pipe, 1000 m of 80 mm GI(M) pipe, 1250 m of 100 mm GI(M) pipe, 3060 m of 90 mm PVC 10 kg pipe and 3060 m of 110 mm PVC 10 kg pipe............ Laid 6600 m of 100 mm DI K9 pipe, 400 m of 150mm DI K9 pipe, 1000 m of 80 mm GI(M) pipe, 1250 m of 100 mm GI(M) pipe, 3045 m of 90 mm PVC 10 kg pipe and 3060 m of 110 mm PVC 10 kg pipe. Laying work and interconnection works are almost completed, balance work is in progress. GLSR at Arayanjalimon-Perunkavumala completed |
Adoor Project Dn AE 4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
08/06/2020 |
Scheduled date of Completion of the Project |
31 Mar 2022 |
Expected date of Completion |
31/03/2022 |
Processing Dates
AS Date |
17 Jan 2019 |
TS Date |
23 Jan 2020 |