| Project | Jal Jeevan Mission (JJM)- Alappuzha District - Providing Functional House hold Tap Connections (FHTC) in Thanneermukkom Panchayath and allied works |
|---|---|
| Project Code | ALPJJM08204201P1 |
| Type | Package |
| Main Project | Jal Jeevan Mission (JJM)- Alappuzha District - Providing Functional House hold Tap Connections (FHTC) in Thanneermukkom Panchayath and allied works (4114 FHTC's) |
| Funding Agency | JJM |
| Category | JJM |
| Type of scheme | Water Supply |
| Scheme | 4215-01-102-92-01 |
| Description | Jal Jeevan Mission (JJM)- Alappuzha District - Providing Functional House hold Tap Connections (FHTC) in Thanneermukkom Panchayath and allied works |
| Status | On-going |
| District | Alappuzha |
| Executing Office | Cherthala PH Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 52700000 |
| TS Number | 6565/2020-2021 |
| Technical specification | Providing Functional House hold Tap Connections (FHTC) in Thanneermukkom Panchayath and allied works |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 08/10/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 15 Apr 2021 |
| Expected date of Completion | 31/07/2022 |
| TS Date | 27 Aug 2019 |
|---|---|
| Estimate Approval | 27 Aug 2020 |
| NIT Approval | 28 Aug 2020 |
| Tender Closing | 09 Sep 2020 |
| Technichal Pre-Qualification | 11 Sep 2020 |
| Price bid opening | 11 Sep 2020 |
| Workorder Date | 24 Sep 2020 |
|---|---|
| NA | 16 Oct 2020 |
| Cherthala PH Section - AE |
| Date: 08/11/2022 |
Work has been completed | 100% Completed
4199 FHTCs completed in package I and package II also completed. 340 FHTCs also to be provided for full saturation. Revised Estimate with comparative statement submitted for Revised AS. Final bill submitted to subdivision for 4199 FHTCs on 21/10/2022.
| Cherthala PH Section - AE |
| Date: 26/10/2022 |
Work has been completed | 100% Completed
4199 FHTCs completed in package I and package II also completed. 340 FHTCs also to be provided for full saturation. Revised Estimate with comparative statement submitted for Revised AS. Final bill submitted to subdivision for 4199 FHTCs.