DEPOSIT-DEPOSIT WORK-2022-23 - ALAPPUZHA DISTRICT PANCHAYATMUTHUKULAM DIVISION ( PROJECT No.S0001/23)- RWSS TO KARTHIKAPPALLY - PIPE LINE EXTENSION IN KODALIPARAMBU TO LIFE SANKETHAM (WARD-3) OF KARTHIKAPPALLY GRAMA PANCHAYATH

Project DEPOSIT-DEPOSIT WORK-2022-23 - ALAPPUZHA DISTRICT PANCHAYATMUTHUKULAM DIVISION ( PROJECT No.S0001/23)- RWSS TO KARTHIKAPPALLY - PIPE LINE EXTENSION IN KODALIPARAMBU TO LIFE SANKETHAM (WARD-3) OF KARTHIKAPPALLY GRAMA PANCHAYATH
Project Code ALPDEPO032313989
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-DEPOSIT WORK-2022-23 - ALAPPUZHA DISTRICT PANCHAYATMUTHUKULAM DIVISION ( PROJECT No.S0001/23)- RWSS TO KARTHIKAPPALLY - PIPE LINE EXTENSION IN KODALIPARAMBU TO LIFE SANKETHAM (WARD-3) OF KARTHIKAPPALLY GRAMA PANCHAYATH
Status Completed
District Alappuzha
Executing Office Harippad PH Sn
AS Amount (Rs) 170000
AS Number H L-2450(7)/22
TS Amount (Rs) 170000
TS Number ORDER No.: WRD/KWA-CE(CR)/EST_TS/8051/2022_26_1_1 Dated: 10-04-2023
Total Bill Submitted (Rs) 76076
Total Bill Paid (Rs) 73496
Population Benefitted 1000
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage DEPOSIT-DEPOSIT WORK-2022-23 - ALAPPUZHA DISTRICT PANCHAYATMUTHUKULAM DIVISION ( PROJECT No.S0001/23)- RWSS TO KARTHIKAPPALLY - PIPE LINE EXTENSION IN KODALIPARAMBU TO LIFE SANKETHAM (WARD-3) OF KARTHIKAPPALLY GRAMA PANCHAYATH

Packages

No. Project Name Location View
1 DEPOSIT-DEPOSIT WORK-2022-23 - ALAPPUZHA DISTRICT PANCHAYATMUTHUKULAM DIVISION ( PROJECT No.S0001/23)- RWSS TO KARTHIKAPPALLY - PIPE LINE EXTENSION IN KODALIPARAMBU TO LIFE SANKETHAM (WARD-3) OF KARTHIKAPPALLY GRAMA PANCHAYATH Harippad PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Jul 2023 Work Completed & Bill Submitted Harippad PH Sn - AE
19 Jul 2023 Work in progress Harippad PH Sn - AE
13 Jul 2023 Work in progress Harippad PH Sn - AE
10 Jul 2023 Work in progress Harippad PH Sn - AE
06 Jul 2023 Work in progress Harippad PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 27/04/2023
Scheduled date of Completion of the Project 26 Jul 2023
Expected date of Completion 26/07/2023

Processing Dates

AS Date 21 Mar 2023
TS Date 10 Apr 2023

Other details