Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of 5 Nos Vertical Turbine pump sets at Head Works, Chowara
Project |
Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of 5 Nos Vertical Turbine pump sets at Head Works, Chowara |
Project Code |
EKMRKI042211850P4 |
Type |
Package |
Main Project |
Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of pumping stations
|
Funding Agency |
RKI |
Category |
RKI |
Type of scheme |
Water Supply |
Scheme |
5475-00-115-94-05 |
Description |
Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of 5 Nos Vertical Turbine pump sets at Head Works, Chowara |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Chowara HW Sn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
750000 |
TS Number |
TS/2022-2023/2022/25509 Dated: 19-07-2022 |
Technical specification |
NIL |
Contractor |
PROFICIENT AUTOMATION AND CONTROLS LIMITED (Mob: 9567863500) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
11/08/2022 |
Scheduled date of Completion as per agreement |
30 Sep 2022 |
Expected date of Completion |
11/02/2023 |
Processing Dates
TS Date |
19 Jul 2022 |
Estimate Approval |
19 Jul 2022 |
NIT Approval |
19 Jul 2022 |
Tender Closing |
06 Aug 2022 |
Technichal Pre-Qualification |
19 Jul 2022 |
Price bid opening |
09 Aug 2022 |
Approval Dates
Workorder Date |
11 Aug 2022 |
NA |
22 Aug 2022 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Aluva PH Dn EE |
Date: 12/02/2024 |
Work has been completed | 100% Completed
Biil Amount 5.99lakhs paid based on State Plan under various heads - BIMS Release Report 2023-24.
Chowara AE |
Date: 05/06/2023 |
Work has been completed | 100% Completed
Work completed and bill submitted.