JJM - 2020-21 - CWSS to Kuzhalmannam, Kannadi and Thenkurissi panchayaths - Pipe line extension and providing FHTCs in Thenkurissi Panchayath in Palakkad District

Project JJM - 2020-21 - CWSS to Kuzhalmannam, Kannadi and Thenkurissi panchayaths - Pipe line extension and providing FHTCs in Thenkurissi Panchayath in Palakkad District
Project Code PKDJJM08205564
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM - 2020-21 - CWSS to Kuzhalmannam, Kannadi and Thenkurissi panchayaths - Pipe line extension and providing FHTCs in Thenkurissi Panchayath in Palakkad District
Status Completed
District Palakkad
Executing Office Kuzhalmannam Sn
AS Amount (Rs) 3400000
AS Number GO(Rt)No 541/2020/WRD
TS Amount (Rs) 3400000
TS Number TS/2020-21/2019/22485
Total Bill Submitted (Rs) 2740984
Total Bill Paid (Rs) 1844426
Population Benefitted 750
Capacity in MLD 9.50
Actual Project Completion Date Date is not specified
Coverage work in progress

Packages

No. Project Name Location View
1 JJM - 2020-21 - CWSS to Kuzhalmannam, Kannadi and Thenkurissi panchayaths - Pipe line extension and providing FHTCs in Thenkurissi Panchayath in Palakkad District Palakkad PH Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Jun 2021 Work completed.Bill submitted. Palakkad PH Dn EE
08 Mar 2021 Work completed ,Preparing Bill Palakkad PH Dn EE
05 Mar 2021 Given 150 no of FHTCs out of 150 . Palakkad PH Dn EE
10 Feb 2021 Given 78 no of FHTCs out of 150 . Palakkad PH Dn EE
28 Jan 2021 Progressing pipe laying works ,3000 mtr length of PVC pipe laid out of 3300m Delay happened since the shortage of pipe . Palakkad PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 31/10/2020
Scheduled date of Completion of the Project 09 Nov 2020
Expected date of Completion 20/02/2021

Processing Dates

AS Date 21 Aug 2020
TS Date 27 Aug 2020

Other details

Project Officers View