- Home
- JAL JEEVAN MISSION - Pipe line extension...
JAL JEEVAN MISSION - Pipe line extension , Erection of Pump set , Replacement of Ac pipe and providing FHTC in Kadakkal Panchayath - Phase II
Project |
JAL JEEVAN MISSION - Pipe line extension , Erection of Pump set , Replacement of Ac pipe and providing FHTC in Kadakkal Panchayath - Phase II |
Project Code |
KLMJJM08204208 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Pipe line extension , Erection of Pump set , Replacement of Ac pipe and providing FHTC |
Status |
On-going |
District |
Kollam |
Executing Office |
Kadakkal PH Sn |
AS Amount (Rs) |
225000000
|
AS Number |
G.O.(Rt)No.541/2020/WRD of 2020-2021 |
TS Amount (Rs) |
149300000 |
TS Number |
TS/2020-2021/2020/20370 |
Total Bill Submitted (Rs) |
73001133 |
Total Bill Paid (Rs) |
68966513 |
Population Benefitted |
25000 |
Capacity in MLD |
2.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
House holds in Kadakkal Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JAL JEEVAN MISSION - Pipe line extension , Erection of Pump set , Replacement of Ac pipe and providing FHTC in Kadakkal Panchayath - Phase II |
Kadakkal PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
18 Sep 2022 |
2352/6147 connections provided at various wards and pump set supplied , now road restoration works in progress. |
Kottarakkara PH Dn EE |
|
28 May 2022 |
36% completed |
Kottarakkara PH Dn EE |
|
04 May 2022 |
2552 FHTC Completed. Pipelaying work also in progress |
Kottarakkara PH Dn EE |
|
06 Mar 2022 |
2250 fhtc completed and pipelaying work is in progress |
Kottarakkara PH Dn EE |
|
28 Feb 2022 |
2119 FHTC Completed and work is in progress |
Kottarakkara PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
08/02/2021 |
Scheduled date of Completion of the Project |
07 Jul 2022 |
Expected date of Completion |
31/08/2023 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
18 Sep 2020 |