JAL JEEVAN MISSION - Pipe line extension , Erection of Pump set , Replacement of Ac pipe and providing FHTC in Kadakkal Panchayath - Phase II

Project JAL JEEVAN MISSION - Pipe line extension , Erection of Pump set , Replacement of Ac pipe and providing FHTC in Kadakkal Panchayath - Phase II
Project Code KLMJJM08204208
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Pipe line extension , Erection of Pump set , Replacement of Ac pipe and providing FHTC
Status On-going
District Kollam
Executing Office Kadakkal PH Sn
AS Amount (Rs) 225000000
AS Number G.O.(Rt)No.541/2020/WRD of 2020-2021
TS Amount (Rs) 149300000
TS Number TS/2020-2021/2020/20370
Total Bill Submitted (Rs) 73001133
Total Bill Paid (Rs) 68966513
Population Benefitted 25000
Capacity in MLD 2.00
Actual Project Completion Date Date is not specified
Coverage House holds in Kadakkal Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JAL JEEVAN MISSION - Pipe line extension , Erection of Pump set , Replacement of Ac pipe and providing FHTC in Kadakkal Panchayath - Phase II Kadakkal PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Sep 2022 2352/6147 connections provided at various wards and pump set supplied , now road restoration works in progress. Kottarakkara PH Dn EE
28 May 2022 36% completed Kottarakkara PH Dn EE
04 May 2022 2552 FHTC Completed. Pipelaying work also in progress Kottarakkara PH Dn EE
06 Mar 2022 2250 fhtc completed and pipelaying work is in progress Kottarakkara PH Dn EE
28 Feb 2022 2119 FHTC Completed and work is in progress Kottarakkara PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 08/02/2021
Scheduled date of Completion of the Project 07 Jul 2022
Expected date of Completion 31/08/2023

Processing Dates

AS Date 21 Aug 2020
TS Date 18 Sep 2020

Other details

Project Officers View