DEPOSIT WORK - KRFB :- TEMPORARY REALIGNMENT OF PIPE LINE OVER PATHIYOOR BRIDGE USING 110 MM HDPE LINE FOR CONSTRUCTION OF NEW BRIDGE NEAR PATHIYOOR TEMPLE IN PATHIYOOR PANCHAYAT.

Project DEPOSIT WORK - KRFB :- TEMPORARY REALIGNMENT OF PIPE LINE OVER PATHIYOOR BRIDGE USING 110 MM HDPE LINE FOR CONSTRUCTION OF NEW BRIDGE NEAR PATHIYOOR TEMPLE IN PATHIYOOR PANCHAYAT.
Project Code ALPDEPO101910144
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT WORK - KRFB :- TEMPORARY REALIGNMENT OF PIPE LINE OVER PATHIYOOR BRIDGE USING 110 MM HDPE LINE FOR CONSTRUCTION OF NEW BRIDGE NEAR PATHIYOOR TEMPLE IN PATHIYOOR PANCHAYAT. SANCTION ACCORDED FOR CONSTRUCTION OF TWO NEW BRIDGES (AT MALAYIL AND PATHIYOOR) THROUGH KRFB. SO, KRFB DEPOSITED PIPE LINE SHIFTING CHARGES AMOUNTING RS1230000/- TO KWA. KWA CARRIED OUT TEMPORARY AND PERMANENT SHIFTING OF PIPE LINES AT MALAYIL BRIDGE. TEMPORARY SHIFTING OF PIPE LINERS OVER PATHIYOOR BRIDGE (200 MM CI /MS) WAS ARRANGED AS QUOTATION WORK USING 110 MM PVC PIPE AND LAYING OF PVC PIPE LINE IS PROPOSED OVER THE TEMPORARY SAND BUND. TO LAY PIPE LINE OVER SAND BUND, PIPE LINE IS TO BE CROSSED THROUGH SOME PRIVATE PROPERTIES. NOW, THERE IS SOME LAND ISSUES AND HENCE, IT MAY NOT POSSIBLE TO LAY PIPE LINE THROUGH BUND. HENCE, AS PER DIRECTION OF HON. MLA'S REVIEW MEETING DATED 21/03/2022, JOINT INSPECTION DONE WITH OFFICIALS OF KRFB ON 23/03/2022 AND DECIDED TO LAY PIPE LINE THROUGH UNDER WATER USING HDPE PIPE. THE REVISED ESTIMATE IS PREPARED BASED ON THE LETTER NO. KRFB-PMU/ALP/EE-1-8/2021 DATED 25.03.2022 FROM EXECUTIVE ENGINEER, KRFB-PMU ALAPPUZHA FOR TEMPORARY REALIGNMENT OF PIPE LINE IN BRIDGE PORTION IN CONNECTION WITH CONSTRUCTION OF NEW BRIDGE.THE DETAILS OF DEPOSITED AMOUNT, UTILIZED AMOUNT AND BALANCE AMOUNT WITH KWA ETC IS ATTACHED IN DETAILS 3. OUT OF DEPOSITED RS1230000/- , THE EXPENDITURE INCURRED IS ONLY RS135090/-. HENCE, SUFFICIENT FUND AVAILABLE WITH KWA FOR EXECUTION OF THIS WORK AS WELL AS FOR PERMANENT LAYING OF PIPE LINE OVER THE BRIDGE AFTER CONSTRUCTION OF NEW BRIDGE
Status Completed
District Alappuzha
Executing Office Kayamkulam PH Sn
AS Amount (Rs) 1230000
AS Number 12/PWD004-93/PD/PMU-KRFB/137R/ALPY/2017
TS Amount (Rs) 191000
TS Number ORDER No. TS/2021-2022/2022/12171 Dated: 29-03-2022
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 1000
Capacity in MLD 1.00
Actual Project Completion Date 03 May 2022
Coverage Pathiyoor bridge
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 DEPOSIT WORK - KRFB :- TEMPORARY REALIGNMENT OF PIPE LINE OVER PATHIYOOR BRIDGE USING 110 MM HDPE LINE FOR CONSTRUCTION OF NEW BRIDGE NEAR PATHIYOOR TEMPLE IN PATHIYOOR PANCHAYAT. Kayamkulam PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 May 2022 work completed Kayamkulam AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 08/04/2022
Scheduled date of Completion of the Project 22 Apr 2022
Expected date of Completion 30/04/2022

Processing Dates

AS Date 10 Oct 2019
TS Date 29 Mar 2022